Updated 5 November 2026. We re-read the 22 October reports, read BMRCL's progress figures for the Hebbal–airport section and the Supreme Court's 26 October order on the Hebbal land, and searched for anything newer. We found no BMRCL notice after 22 October that changes the airport dates. BMRCL itself calls these "proposed schedules, not confirmed opening dates" (as quoted by The Bengaluru Live).

Hebbal to airport: progress figures, 22 October 2026

From BMRCL's release after Minister Krishna Byre Gowda's site review, as reported by The Bengaluru Live (22 October 2026):

  • Phase 2B, KR Puram to airport (38.44 km): 61.5% overall physical progress.
  • Hebbal to airport: U-girder erection 95% done; track laid on 18.6 of 52.9 track km; station entry and exit works 41% done.
  • KR Puram to Kempapura: piling complete; piers 73%; U-girders 66%; track laying not yet started (20.4 track km needed).
  • Target: Airport–Hebbal by end-2027; Hebbal–KR Puram in early 2028.
  • For comparison, Phase 2A, Silk Board to KR Puram (19.75 km): 87% overall, commissioning around mid-2027, subject to statutory clearances.

Airport metro opening date: what each report says

Our reading: the newest BMRCL figures point to end-2027 for Hebbal to KIA. September 2027 is the earliest date in circulation and is older. The November 2027 (KR Puram to airport) and early-2028 (Hebbal–KR Puram) dates, both from 22 October, do not fit neatly together, and we found no BMRCL notice that settles it. If the section opens alone, it would run Hebbal to the airport without a link to the rest of the city's lines until KR Puram to Hebbal is ready, and we found no official word on whether BMRCL will open it that way.

  • 26 October 2026, Deccan Herald: the Supreme Court allowed BMRCL to go ahead with Blue Line construction on the disputed Hebbal land. BMRCL's plea said about 84% of the work on the corridor was complete and that it was scheduled to be commissioned by June 2027; the report does not say which section that date covers. Our explainer: Blue Line Hebbal Stretch: Supreme Court Lets Work Go On
  • 22 October 2026, The Bengaluru Live (BMRCL release): Airport–Hebbal by end-2027; Hebbal–KR Puram early 2028.
  • 22 October 2026, Deccan Herald (re-read on 5 November): the 38.44 km KR Puram to Hebbal to airport stretch, with Namma Metro promising to start train operations by November 2027.
  • 9 October 2026, Channel IAM: Hebbal to KIA targeted for September 2027; KR Pura to Hebbal likely December 2027 to March 2028; full line March 2028. No official is named for these dates.
  • 24 August 2026, Metro Rail News: airport section September or October 2027, replacing the earlier June 2027 date, after a review by Minister Krishna Byre Gowda; full line March 2028.
  • 20 August 2026, Deccan Herald (as read by us on 17 October): Hebbal to airport unlikely before September 2027. It said trial runs and commissioning take at least six months after civil work.

What is holding up the Hebbal to airport line?

  • Hebbal: construction is a main bottleneck, with clearances needed along the Outer Ring Road in the Nagawara to Hebbal area (Metro Rail News, 24 August 2026).
  • Yelahanka IAF to airport terminal: about 80% complete in August, with more time sought to March 2027 (Deccan Herald, 20 August 2026, as read by us on 17 October).
  • Hebbal to Kasturi Nagar: officials cited Cauvery pipelines and underground drainage lines, mainly between Veerannapalya and Hebbal (Deccan Herald, 22 October 2026, as read by us on 23 October).
  • Construction World said on 28 October 2026 that the section is behind schedule and the minister directed officials to speed up.

Hebbal to airport metro stations

Heading north from Hebbala: Kodigehalli, Jakkur Cross, Yelahanka, Bagaluru Cross, Doddajala, Airport City and KIAL Terminals (Wikipedia, as listed in our station guide). KIAL Terminals is underground and Airport City is at grade. All 29 stations: Airport Metro Line Bangalore: 29 Stations, Oct 2026 Status

When can you ride from Silk Board or MG Road to the airport?

From Silk Board, only when the full Blue Line runs, which is targeted for March 2028. From MG Road, you would take the Pink Line to Nagawara and change to the Blue Line. That needs the Pink Line underground (target March 2027) and the KR Puram to Hebbal section, which includes Nagawara. Our arithmetic from those dates: do not count on either route before the KR Puram to Hebbal section is running.

What should buyers near Yelahanka and Devanahalli do?

  • Price the home on today's road commute. Add the metro as an upside, not a certainty.
  • Ask how far the actual station entrance is, not the 'metro corridor'.
  • A builder's brochure date is not a BMRCL date. Check the newest dated news report yourself.
  • See the area guide: The Bangalore Airport Corridor: An Infrastructure & Property Guide