578 approved project registrations in Bengaluru Urban and Bengaluru Rural have a K-RERA completion date between 1 December 2026 and 31 December 2027, by our count of the full register. 394 are residential or group housing, 161 are plotted layouts, 12 are mixed developments and 11 are commercial.

Updated 7 November 2026. We downloaded and read every row of both district registers on the Karnataka RERA portal today (5,183 rows), kept approved registrations, removed transfer-of-registration records and counted by the 'proposed date of completion' column. A project can have several registrations, one per phase or wing, so 578 is a count of registrations, not of separate projects.

How many registrations complete in each month?

K-RERA completion dates, Bengaluru Urban and Bengaluru Rural, read 7 November 2026 (R = residential or group housing, P = plotted, O = mixed or commercial):

  • December 2026: 175 (R 128, P 44, O 3). 152 of them carry 31 December 2026.
  • January 2027: 20 (R 11, P 8, O 1)
  • February 2027: 12 (R 5, P 4, O 3)
  • March 2027: 69 (R 46, P 20, O 3)
  • April 2027: 15 (R 11, P 2, O 2)
  • May 2027: 15 (R 10, P 5, O 0)
  • June 2027: 49 (R 39, P 8, O 2)
  • July 2027: 12 (R 9, P 3, O 0)
  • August 2027: 22 (R 17, P 3, O 2)
  • September 2027: 20 (R 14, P 3, O 3)
  • October 2027: 22 (R 15, P 7, O 0)
  • November 2027: 7 (R 2, P 5, O 0)
  • December 2027: 140 (R 87, P 49, O 4). 125 of them carry 31 December 2027.

Which quarters are busiest?

Completion dates bunch at quarter-ends and especially at year-end, because many promoters declare the last day of a month or year when they register. By quarter: December 2026 alone has 175; January to March 2027 has 101; April to June 2027 has 79; July to September 2027 has 54; and October to December 2027 has 169.

For a buyer this means two things. First, the choice of homes with a completion date in the next 14 months is wide, at 394 residential registrations. Second, a 31 December date is the promoter's declared date for that registration, not the week you will get keys; handover usually follows the occupancy certificate, tower by tower.

Where are these projects? Count by taluk

Bengaluru East has the most residential registrations due in the window. The airport side (Devanahalli, Doddaballapura) is mostly plots. Taluk is the register's own field; the localities in brackets are examples, and a project's exact village is on its K-RERA detail page.

  • Bengaluru East (Whitefield, KR Puram, Varthur, Mahadevapura side): 156 (135 residential, 11 plotted, 10 mixed or commercial)
  • Bengaluru South (Kanakapura Road, Bannerghatta Road, JP Nagar, Begur, Kengeri side): 121 (96 residential, 19 plotted, 6 mixed or commercial)
  • Anekal (Electronic City, Chandapura, Attibele, Sarjapura, Jigani): 114 (64 residential, 49 plotted, 1 mixed)
  • Bengaluru North (Hebbal, Thanisandra, Jakkur, Yeshwanthpur, Jalahalli side): 57 (48 residential, 3 plotted, 6 mixed or commercial)
  • Devanahalli (airport side): 53 (13 residential, 40 plotted)
  • Hosakote: 33 (16 residential, 17 plotted)
  • Yelahanka: 33 (22 residential, 11 plotted)
  • Doddaballapura: 7 (all plotted). Nelamangala: 4 (all plotted).

When were these projects registered?

By the 'approved on' date in the same register: 138 were approved in 2025, 137 in 2024, 121 in 2023, 87 in 2022, 22 in 2021 and 33 in 2026 to date; 40 were approved between 2017 and 2020. Most of the pipeline due by December 2027 was registered in the last three years.

Some catalogue projects with a date in this window

For the 2027 dates grouped by area see Bangalore Projects With Possession in 2027: Dates by Area, and for budget picks see Under-Construction Flats Bangalore Under ₹2 Cr by Dec 2027

  • Prestige Lavender Fields, Varthur: RERA completion date 31 May 2027. PRM/KA/RERA/1251/446/PR/290423/005906. See Prestige Lavender Fields
  • Prestige Glenbrook, Nallurahalli, Whitefield: 30 June 2027. PRM/KA/RERA/1251/446/PR/081123/006382. See Prestige Glenbrook
  • Sobha Victoria Park Phase 1, Hennur Road: 31 December 2027. PRM/KA/RERA/1251/309/PR/310322/004800. See Sobha Victoria Park
  • Cielo at Brigade Valencia, Bommasandra, Hosur Road: 31 December 2027. PRM/KA/RERA/1251/308/PR/120123/005613. See Brigade Valencia
  • Purva Park Hill (Wing A), off Kanakapura Road: 31 December 2027. PRM/KA/RERA/1251/310/PR/220601/004946. See Purva Park Hill
  • Shriram Esquire, Koramangala: 19 January 2027. PRM/KA/RERA/1251/310/PR/080223/005702. See Shriram Esquire

What the wider market numbers say

ANAROCK's Q3 2026 data, reported by Business Today on 29 September 2026, put Bengaluru home sales at about 16,670 units in July to September 2026, up 12% year on year, with new supply up 17% and prices up 8%. Those are quarterly sales and launch figures; the 578 above is a count of registrations with a completion date in the window, a different measure, so the two should not be added or compared directly.

How to read a K-RERA completion date