No research house has published a Bangalore property price forecast for 2030. The longest published calls run to about 2028: ANAROCK (January 2026) expects average prices in the top seven cities, Bengaluru included, to be 24% higher in 2028 than in 2025, and a Reuters poll of analysts (March 2026) put Bengaluru and other big cities at 5–7% a year for three years. What is dated to 2030 is infrastructure: the Blue Line by March 2028, suburban rail between December 2028 and March 2030, and the Red Line by April 2033.
Updated 7 November 2026. Every date and forecast below is the named source's own, with its date. Any '2030 price' you see quoted without a research house and date behind it is not one of these.
The longest published forecasts
- ANAROCK, January 2026: average capital prices in the top seven cities expected to rise 24% in 2028 over 2025, and new supply to grow 24% by 2028 from about 4.19 lakh units in 2025. Not Bengaluru-only.
- ANAROCK, January 2026: global capability centres in India expected to grow from about 1,700 in 2025 to 2,400 by 2030, and their staff from 19 lakh to 28 lakh. ANAROCK links this job growth to rental demand. National figures.
- Reuters poll of property analysts, 23 February to 10 March 2026: Mumbai, Delhi, NCR, Bengaluru and Chennai prices could rise 5–7% over the next three years; national average about 5% a year through 2028.
- India Ratings, February 2026: Bengaluru price growth to moderate but stay above 10% in FY27, which ends March 2027.
Bengaluru's infrastructure timeline to 2033
Each line: project · target · who set or reported it, and when.
- 2026: Pink Line elevated, Kalena Agrahara–Tavarekere, opening reported for 13 November 2026 (Oneindia, 2 November 2026).
- 2026–27: STRR Hoskote–Hosur stretch, December 2026 in phases; rail overbridge March 2027 (Oneindia, 23 October 2026).
- 2027: KWIN City plot allotment to investors from February–March 2027 (newkerala, 16 October 2026).
- 2027: Pink Line underground, Dairy Circle–Nagawara (Oneindia, 2 November 2026); Blue Line Silk Board–KR Puram, possibly mid-2027 (Swarajya, 16 August 2026).
- 2027–28: Blue Line Hebbal–airport, end-2027 or October–November 2027; KR Puram–Hebbal early 2028; full line March 2028 (Transclew, 23 October 2026).
- About 2028–29: Bengaluru Business Corridor phase one (68.36 km); three-year contract, government asked for two (Construction World, 31 July 2026).
- December 2028: suburban rail Corridor-2, Chikkabanavara–Yeshwanthpur–Bennigenahalli (K-RIDE, in Knight Frank H1 2026).
- March 2029: suburban rail Corridor-4, Heelalige–Bennigenahalli–Rajanukunte (K-RIDE).
- March 2030: suburban rail Corridor-1, city–Yelahanka–Devanahalli–airport, and Corridor-3, Kengeri–Cantonment (K-RIDE).
- About 2032: metro Phase 3 on Outer Ring Road West and Magadi Road; BMRCL deadline not finalised (The Metro Rail Guy estimate, February 2026).
- April 2033: Red Line, Sarjapur–Hebbal (Asianet Newsable, 15 July 2026), awaiting central clearance as of 29 July 2026 (Oneindia).
- No date yet: Hoskote metro link, at DPR stage (Construction World, 8 October 2026); Greater Bengaluru Integrated Township at Bidadi, land notifications issued for over 7,335 acres by 30 October 2026 (The News Minute, 2 November 2026).
How Bengaluru got here: the published record
- Prices: ANAROCK's average rose from ₹4,975 per sq ft in 2019 to ₹9,450 in Q2 2026, up 90% (Business Today, 4 August 2026).
- Rental yield: 3.6% in 2019 to 4.6% in Q2 2026 on ANAROCK's data.
- Latest year: Knight Frank's weighted average up 9% to ₹9,354 per sq ft in H1 2026; ANAROCK up 8% year on year in Q3 2026.
- Supply now: about 80,200 unsold homes and a 15-month overhang (ANAROCK, Q3 2026).
Reading a 2030 claim
A useful test for any long-range price claim: who made it, when, for which area, and on which measure. The forecasts above meet that test but stop around 2028; the 2030 story in published sources is about jobs and transport rather than a price. Dates for transport projects have moved before, so the source and date are given for each.
For the full metro picture, see Bangalore Metro Opening Dates 2026-2028: Every Line, and for suburban rail stations, Bangalore Suburban Rail Stations: All 4 Lines, 2026 Status. Offices and the homes near them: GCCs in Bangalore 2026: Where They Are, Homes Nearby