Updated 5 November 2026. We read CAQM's order of 2 November 2026 and the revised GRAP schedule of 29 September 2026 that it encloses. We found no Stage 3 order and no revocation of Stage 2 as of today. The title of this guide changed from Stage 1 to Stage 2 to match the stage in force.

GRAP orders this winter: dates and stages

  • 29 September 2026: CAQM issues the revised GRAP schedule for the NCR (cited in its later orders)
  • 21 October 2026: Stage 1 ('Poor', Delhi AQI 201–300) invoked across the NCR; Gurugram's AQI was 216 that day (Business Today, 22 October)
  • 31 October 2026: Delhi AQI 117 ('Moderate') (CAQM order)
  • 1 November 2026: Delhi AQI 261 ('Poor') (CAQM order)
  • 2 November 2026: Delhi AQI 324 ('Very Poor'); Stage 2 invoked in the entire NCR with immediate effect, with Stage 1 and 2 actions running together (CAQM order No. 120017/27/GRAP/2021/CAQM)
  • 5 November 2026: no Stage 3 order or revocation found; check caqm.nic.in for the current stage

What does GRAP Stage 2 change in Gurugram?

Stage 2 in the revised schedule has eight actions. The ones a Gurugram home owner or buyer will notice:

  • Construction sites: inspections for dust-control compliance are to be intensified. There is no stop-work order at this stage.
  • Roads: daily mechanical or vacuum sweeping and water sprinkling with dust suppressants on identified roads, before peak hours
  • Parking: urban local bodies are to raise parking fees to discourage private vehicles
  • Housing societies: RWAs must provide electric heaters to security, sanitation, horticulture and other staff, so they do not burn biomass or waste in winter
  • Offices: state governments are to stagger timings of public offices and municipal bodies in Gurugram, among other districts
  • Citizen charter: avoid dust-generating construction from October to January, use public transport, and work from home where your job allows

GRAP stages and AQI thresholds

  • Stage 1, Poor, Delhi AQI 201–300: construction continues under dust controls; sites of 500 sq m or more must be registered on the state dust-monitoring portal (CAQM schedule, 29 September 2026)
  • Stage 2, Very Poor, AQI 301–400: no construction ban; more inspections (CAQM schedule)
  • Stage 3, Severe, AQI 401–450: dust-generating construction stops across the NCR except on exempt project types (CAQM schedule)
  • Stage 4, Severe Plus, AQI above 450: linear public projects such as highways, flyovers and pipelines lose their Stage 3 exemption (CAQM schedule)
  • Each stage adds to the earlier ones. A stage can be invoked in advance on forecasts, and the stages follow Delhi's AQI but apply to the whole NCR.

What stops at Stage 3, including inside your flat?

If CAQM invokes Stage 3, the schedule lists these activities for strict restriction across the NCR:

  • Earthwork, excavation and filling, boring, drilling and piling
  • All demolition
  • Open-trench laying of sewer, water, drainage and electric lines
  • Brick and masonry work, and RMC batching plants
  • Major welding and gas cutting (minor welding for mechanical, electrical and plumbing work is allowed)
  • Painting, polishing and varnishing
  • Cement, plaster and other coatings, except minor indoor repairs or maintenance
  • Cutting, grinding and fixing of tiles, stone and other flooring, except minor indoor repairs or maintenance
  • Moving or loading dust-generating materials such as cement, fly ash, bricks and sand, and moving construction vehicles on unpaved roads

Less dust-generating work may continue under the C&D waste rules and dust norms. Railway, metro, airport and ISBT projects, defence and national-importance projects, hospitals, linear public projects and sanitation and water projects keep working at Stage 3. Private housing is not on that list.

For a buyer this matters in two ways. A developer's tower work can pause. And if you have just taken possession, a fit-out with painting, false ceilings that need plastering, or new flooring may have to wait until the stage is lifted. That applies to painting, plaster work and new flooring, beyond minor indoor repairs. Stage 3 also restricts BS-III petrol and BS-IV diesel cars in Gurugram, moves classes up to Class V to hybrid mode in Gurugram, and asks the state to decide on 50% office attendance.

What changed in the revised GRAP (schedule of 29 September 2026)

CAQM's revised schedule, dated 29 September 2026 and reported as applying from 1 October, has 48 actions: 25 under Stage 1, 8 under Stage 2, 10 under Stage 3 and 5 under Stage 4 (Sunday Guardian; we counted the same in the schedule). Two shifts matter for Gurugram residents: rules on diesel generator sets moved from Stage 2 to Stage 1, and restrictions on BS-IV and older buses from the NCR and neighbouring states also moved to Stage 1 (Sunday Guardian). The Stage 3 curb on BS-III petrol and BS-IV diesel cars covers Gurugram, Faridabad, Ghaziabad, Gautam Buddh Nagar and now Sonipat (Sunday Guardian).

The wider November–January curbs reported alongside, including a prohibition on dust-generating demolition and outdoor civil construction from 1 November and a complete construction-and-demolition ban from 10 December to 20 January, are described as part of Delhi's winter plan (Sunday Guardian). We found no report extending those Delhi dates to Gurugram; treat them as Delhi-only unless Haryana or CAQM orders otherwise.

Is construction banned in Gurugram under Stage 1 or Stage 2?

No. Under Stages 1 and 2, work that complies with its permissions and pollution-control norms is allowed, while open burning and dust-generating work that breaches the controls is not (Business Today; CAQM schedule). The site obligations that apply from Stage 1 onwards:

  • Projects on plots of 500 sq m or more must be registered on the state or Delhi portal for remote dust monitoring; work should not be permitted on qualifying projects that are not registered (DesiMachines).
  • Construction material and C&D waste stored covered and moved only in covered vehicles (DesiMachines; Business Today).
  • Dust kept within site boundaries, with anti-smog guns in proportion to the project's built-up area (DesiMachines).
  • An Integrated Command and Control Centre is monitoring construction-related pollution (Business Today).

Society diesel generators: the rule most residents miss

Generator rules now start at Stage 1: the revised schedule places the regulated operation of DG sets under Direction No. 76 (29 September 2023) in Stage 1, item 18, and says DG sets should not be used as a regular source of power. Under that direction, as summarised by DesiMachines: gas-based sets of any capacity, sets up to 800 kW meeting MoEFCC standards, and sets of 800 kW and above with a prescribed emission-control system have no restriction; sets from 41 kW to under 800 kW must run in dual-fuel mode or have certified retrofitted emission-control devices; sets from 19 kW to under 41 kW need dual-fuel mode; and portable sets under 19 kW are generally not permitted except for emergency services.

This matters in Gurugram, where many societies run on diesel backup during outages. Public infrastructure is adapting too: NHAI has begun fitting retrofit emission-control devices on 25 diesel generator sets used for lighting on the 8.7 km Package IV stretch of the Dwarka Expressway, from Basai to the Kherki Daula cloverleaf, in line with CAQM's measures (PropNewsTime, 23 October 2026).

  • Ask your RWA or maintenance agency the capacity of each society generator and whether it has a retrofit device or dual-fuel kit.
  • If you are buying a resale flat, ask whether backup was ever curtailed during last winter's GRAP stages.
  • For a new project, ask the developer what backup technology is specified and whether it is GRAP-compliant.

Does GRAP delay possession of an under-construction flat?

Stages 1 and 2 should not, because work continues. A Stage 3 or 4 order can stop structural work for days or weeks. Whether those days extend the promised possession date depends on the force majeure clause in your builder-buyer agreement and, in a dispute, on how HRERA reads it; we did not find a 2026 HRERA order setting a general rule, so do not assume either way. Practical steps:

  • Read the force majeure clause in your agreement and note whether it names government or court orders on pollution.
  • Keep the CAQM orders' dates. If a developer later cites GRAP for a delay, you can match the claim to the days restrictions were actually in force.
  • Compare the agreement's possession date with the completion date on the project's HRERA registration.