Under section 52(1)(d) of the Karnataka Apartment (Ownership and Management) Act, 2026, a promoter who 'hands over possession of any apartment without obtaining the occupancy certificate' can be fined up to ₹1 lakh, plus up to ₹1,000 for every day the contravention continues. The Act also gives the promoter 60 days from the occupancy certificate (OC) to file the project declaration, hand over the project records and transfer all maintenance deposits and corpus, with interest, to the association.

Updated 8 November 2026. Status: the Act received assent on 9 October 2026 and was published in the Karnataka Gazette (Extraordinary) on 15 October 2026 as Karnataka Act No. 45 of 2026 (Fox Mandal, 16 October 2026). It takes effect from a date the government notifies; we found no commencement notification, rules or Competent Authority as of 8 November, so no one can yet be penalised under it. Quotes are from the Bill as passed by the Legislative Assembly (LA Bill No. 14 of 2026), because we could not open the Act's gazette copy; Fox Mandal's summary of section 52 matches it.

What counts as an occupancy certificate

Section 2(w) defines the OC as the certificate 'by whatever name called' issued by the local authority permitting occupation of a building. Its Explanation adds that, for RERA purposes, 'the final occupancy certificate issued by the Local Authority shall be deemed to be the completion certificate'. So the final OC is the document that matters for both laws. Background on OC and CC: Occupancy Certificate vs Completion Certificate in Bengaluru: What to Demand Before You Take Possession.

The penalties linked to the OC

  • Possession without OC (section 52(1)(d)): up to ₹1 lakh, plus up to ₹1,000 a day while it continues.
  • Not filing the declaration within 60 days of OC (sections 13(1), 52(1)(a)): same penalty.
  • Not facilitating the association (sections 21, 52(1)(b)): same penalty.
  • Not executing the deed of transfer (sections 10, 52(1)(c)): same penalty.
  • Other breaches of the Act, rules or bye-laws by anyone, including not handing over records or funds: up to ₹20,000 per contravention plus up to ₹1,000 a day, and an order to restore (section 52(2)).
  • Company officers in charge of the project are deemed responsible unless they prove due diligence (section 52(5)).
  • Unpaid penalties are recoverable as arrears of land revenue or property tax (section 52(4)).

Three things due within 60 days of the OC

  • Declaration to the Competent Authority (section 13(1)), with land and title details, sanctioned plan, list of flats with private and carpet areas, common and limited common areas, each flat's undivided share and encumbrances (section 14).
  • Original records to the association (section 16(1)(b)): title documents, sanctioned plans and completion certificates, as-built and structural drawings, fire, lift and environmental certificates, insurance, encumbrance certificates, service drawings, equipment warranties and manuals, maintenance contracts, building-management software credentials and tax receipts up to handover.
  • Money to the association (section 16(1)(c)): maintenance deposits, security deposits, corpus and advance maintenance, with interest, plus an audited project-wise and allottee-wise statement.

Buyer checklist at possession

  • Ask for a copy of the final OC before you take keys or pay the last instalment. Under the Act, handing over a flat without one is a contravention.
  • Note the OC date. The 60-day clock for the declaration, records and funds starts then.
  • Check that the OC covers your tower and floor; a partial OC may cover only some blocks.
  • Ask for the draft declaration and compare your undivided share and area figures with your sale agreement. UDS guide: UDS in Apartment Bangalore: Your Land Share, 2026 Rules.
  • Get in writing how and when corpus and advance maintenance will move to the association, with interest.
  • Keep defect lists. Transfer of management does not end the promoter's RERA defect liability (sections 10(8), 21(13)).
  • A recent court ruling on OCs in Bengaluru: Occupancy Certificate Cancelled: Karnataka HC Ruling, Oct 2026. After possession: After Flat Possession in Bangalore: 9 Things to Do (2026).

Who can complain, and where

  • Under section 52(1): the association's secretary, a person authorised by its executive committee, any aggrieved apartment owner, or the Competent Authority on its own.
  • The Competent Authority will be an officer of the local or planning authority, not below Group-B, appointed within three months of commencement (section 38).
  • Appeals: First Appellate Authority within 30 days, then the Second Appellate Authority, then the High Court (sections 41(8), 44, 45, 42(3)).
  • Civil courts cannot hear matters the Act gives to these authorities (section 60). RERA remedies continue alongside; the Act is 'in addition to, and not in derogation of' other laws (section 64).