Updated 7 November 2026. We opened the 'View OC/CC/PCC' record behind every row of HARERA Gurugram's register with a completion date in the window and took the document type and the date recorded against it. An OC can cover only some towers, so treat this as a shortlist to verify, not as proof that every flat is ready.
OC or CC records dated 2026
- M3M Jewel, Sector 25: OC 9 Sep 2026. HRERA GGM/722/454/2023/66, completion date 29 Mar 2027.
- Central 67 by DLF Home Developers, Sector 67: OC/CC record 27 Aug 2026. HRERA GGM/768/500/2023/112, completion date 31 Dec 2027.
- Ashiana Amarah Phase I and IA, Sector 93: OC 22 Jul 2026. HRERA GGM/590/322/2022/65, completion date 15 Jan 2027.
- Godrej Meridien Phase III, Sector 106: OC 15 Jul 2026 (earlier OC records 31 Mar 2023 and 30 Sep 2024). HRERA GGM/393/125/2020/09, completion date 30 Mar 2027. Godrej Meridien
- JMS Premier Floors-II, Sector 95: OC 9 Jun 2026. HRERA GGM/895/627/2024/122, completion date 31 Dec 2026.
- JMS Premier Floors, Sector 95: OC 9 Jun 2026 (and 17 Jun 2025). HRERA GGM/801/533/2024/28, completion date 31 Dec 2026.
- Whiteland Blissville, Sector 76: CC 9 Jun 2026 on all three registrations, GGM/598/330/2022/73, GGM/604/336/2022/79 and GGM/636/368/2022/111, completion date 30 Jun 2027. Whiteland Blissville
- Tulip Yellow, Sector 69: CC 3 Jun 2026. HRERA GGM/376/108/2019/70, completion date 31 Dec 2027.
- M3M Capital, Sector 113: OC 26 May 2026 on both registrations, GGM/612/344/2022/87 (31 Dec 2026) and GGM/531/263/2022/06 (29 Jun 2027). M3M Capital
- M3M Soulitude 2, Sector 89: OC records 15 Apr 2026 and 1 May 2026. HRERA GGM/859/591/2024/86, completion date 3 Apr 2027. M3M Soulitude
- Godrej Meridien I, Sector 106: OC 13 Mar 2026 (and 31 Mar 2023). HRERA GGM/273/2018/05, completion date 31 Dec 2027.
- Palm County, Sector 78: OC/CC record 6 Mar 2026. HRERA GGM/580/312/2022/55, completion date 5 Mar 2027.
- Lykehomes Avenue, Sector 3: CC 2 Mar 2026. HRERA GGM/786/518/2024/13, completion date 31 Oct 2027.
- M3M Route65, Sector 65: OC and CC records 20 Jan 2026 (and an OC of 24 Jun 2025 on the first). HRERA GGM/803/535/2024/30 and GGM/605/337/2022/80, completion date 28 Feb 2027.
OC or CC records dated 2023 to 2025
- Grand Vista by Pyramid Infratech, Sector 73: OC 3 Dec 2025. HRERA GGM/560/292/2022/35, completion date 15 Dec 2026.
- Alameda Central by DLF Home Developers, Sector 73: CC 1 Dec 2025. HRERA GGM/632/364/2022/107, completion date 8 Sep 2027.
- Grand Central 114, Sector 114: OC 17 Nov 2025. HRERA GGM/540/272/2022/15, completion date 18 Jan 2027.
- Manor One, Sector 111: OC 14 Nov 2025 for Towers A, B1, B2, C1, C2, EWS and part basement. HRERA GGM/364/96/2019/58, completion date 30 Jun 2027.
- Green Bhoomi, Sector 99A: CC 7 Nov 2025. HRERA GGM/669/401/2023/13, completion date 25 Jan 2027.
- Samsara Avasa, Sector 63: OC 6 Oct 2025. HRERA GGM/648/380/2022/123, completion date 31 Dec 2026.
- Samsara Vilasa and Samsara Arya, Sector 32: OC 6 Oct 2025. HRERA GGM/647/379/2022/122, completion date 31 Dec 2026.
- Godrej Meridien II, Sector 106: OC 30 Sep 2024. HRERA GGM/274/2018/06, completion date 31 Dec 2027.
- Imperial Estate by Pyramid Infratech, Sector 70A: OC/CC record 16 Dec 2024. HRERA GGM/559/291/2022/34, completion date 20 Dec 2026.
- DDJAY plotted colony by Adhikaansh Realtors and Aawam Residency, Sector 89: OC records 2 Aug 2024. HRERA GGM/500/232/2021/68, completion date 30 Oct 2027.
- Bonheur Avenue, Sector 35 Sohna: CC 18 Jun 2024. HRERA GGM/606/338/2022/81, completion date 31 Dec 2026.
- Godrej Nature Plus, Sector 33 Sohna: OC 3 Apr 2023 and 31 Oct 2023. HRERA 18 of 2018, completion date 29 Jan 2027. Godrej Nature Plus
Why does a project with an OC still show a 2027 HRERA date?
The 'Registration Up-to' date is the end of the registration period the promoter declared for that phase. A tower can receive its OC well before that date, and other towers in the same registration can follow later. That is why Godrej Meridien Phase III shows three OC records from 2023 to 2026 against one registration.
HRERA's record table labels each document as an Occupation Certificate, a Completion Certificate or a Part Completion Certificate (PCC), with a date and a link to the file. Ask the seller for the copy that names your tower, and read Occupation and Completion Certificates in Haryana: What to Check Before You Take Possession before you sign.
Context: how much stock is there in Gurugram?
- Gurugram held 57% of NCR's unsold housing inventory in January to September 2026 (Knight Frank India, via Construction World, 9 Oct 2026).
- NCR had 86,200 unsold homes at the end of Q3 2026, an 18-month overhang, 2% fewer than a year earlier (ANAROCK, via EconoTimes, 22 Oct 2026).
- Neither report splits unsold stock into ready and under-construction homes. The list above is the part a buyer can verify on HRERA today.
Before you buy a ready flat in Gurgaon
- Match the tower on your allotment letter to the OC copy.
- Compare GST and total cost with an under-construction flat: Ready to Move vs Under Construction: Which Is Better? (2026 GST, Tax and Cost Math)
- Check the registry and property ID: How to Verify Registry and Property ID in Gurugram (2026)
- Budget for registration and stamp duty: Property Registration Gurgaon 2026: PAN Check, Process, Charges. Browse ready homes at Ready To Move, Gurgaon