GMDA's new boosting station in Sector 72 is to supply 95 MLD of water to Sectors 58 to 80, adding 40 MLD for the Golf Course Extension Road, Sohna Road and SPR belt, and taking that load off the existing Sector 51 boosting station. GMDA said on 29 September 2026 that commissioning was planned for October 2026.

Updated 8 November 2026. We read GMDA's 29 September and 20 October releases and its service notices, and counted HRERA housing registrations in Sectors 58–80 from our register file. GMDA's news list to 6 November 2026 has no separate commissioning announcement; its 20 October release puts citywide supply at about 770 MLD, the figure it said would follow the station's commissioning.

What GMDA said about the Sector 72 station

  • Supply: 95 MLD to Sectors 58 to 80 once commissioned (GMDA Chief Engineer R.S. Jangra at the 13th District Coordination Committee, reported 29 September 2026).
  • Increase: 40 MLD more for these sectors than today, per the release headline.
  • Load shift: the Sector 72 station takes over Sectors 58–80 from the Sector 51 boosting station.
  • Citywide effect: about 720 MLD supplied today from the Chandu Budhera and Basai treatment plants, rising to 770 MLD after commissioning.
  • Timing: 'next month', i.e. October 2026, per the 29 September release.
  • Related work: GMDA shut the master supply from the Sector 51 station from 30 September to 2 October 2026 for work on a 1,500 mm pipeline (GMDA public notice).

Which areas are in Sectors 58 to 80?

The belt covers Golf Course Extension Road (Sectors 58–63A, 65–66), Sohna Road's southern sectors (67–72), the SPR (69–76) and the first New Gurgaon sectors (77–80). It is one of Gurugram's densest areas of new housing supply.

HRERA Gurugram registrations for housing (group housing, floors, affordable, plotted) in our file, by sector: Sector 58: 11; 59: 10; 60: 8; 61: 5; 62: 14; 63: 9; 63A: 18; 65: 17; 66: 13; 67: 13; 67A: 8; 68: 9; 69: 8; 70: 13; 70A: 16; 71: 11; 72: 1; 73: 7; 74A: 2; 76: 13; 77: 7; 78: 15; 79: 15; 79B: 2; 80: 5. Total: 250, of which 125 have a registered completion date still ahead of 8 November 2026.

What it does not fix on its own

  • Treatment capacity: the boosting station moves and pressurises water; it does not treat more. Treatment expansion is separate: Basai Unit 4 (+100 MLD, ₹149 crore, 30 months; approved July 2026) and a sixth 100 MLD unit at Chandu Budhera for Sectors 81–115 (approved 20 October 2026). See Gurgaon Water Supply 2026: 770 MLD Now, What Comes Next.
  • Last-mile lines: inside a licensed colony, internal water lines are the developer's or the RWA's; GMDA supplies to the master connection.
  • Power: boosting stations need grid power; check a society's backup for its own pumps.
  • Groundwater: GMDA's 5 October 2026 plan asks departments to stop using borewells over time and act against unauthorised ones.

Checks for buyers in this belt