The Silk Board–KR Puram Blue Line (Phase 2A, 19.75 km on the Outer Ring Road) is now targeted to open to passengers by mid-2027, subject to statutory clearances, after a progress review by minister Krishna Byre Gowda; construction was 87% complete and station entry and exit works 88% (Construction World, 28 October 2026; NativePlanet, 23 October 2026). Trial runs from KR Puram towards Marathahalli were due by the end of October, and BMRCL's MD had set 15 November as the trial target (OneIndia citing Moneycontrol, 19 October 2026). We found no report that trials had begun as of 8 November 2026.
Updated 8 November 2026. This page tracks the review and every opening date given this year. Station list and homes near each station are in our earlier post: Blue Line Metro Bangalore Opening Date: Silk Board–KR Puram 2026.
What the October review said
- Progress — 87% overall construction, 88% for station entry and exit works (Construction World, 28 Oct 2026).
- Trials — between KR Puram and Marathahalli by end-October, with trains introduced progressively as stations are commissioned (Construction World, 28 Oct 2026; NativePlanet, 23 Oct 2026).
- Opening — passenger services targeted for mid-2027, subject to statutory clearances; full corridor to Central Silk Board in the middle of 2027 (Construction World, 28 Oct 2026).
- Incomplete works — Marathahalli and Central Silk Board stations (NativePlanet, 23 Oct 2026). The minister told officials to speed up construction.
- Partial opening — BMRCL is considering opening KR Puram–Marathahalli first, but an official said this may not be feasible because required permissions may not be granted (Construction World, 28 Oct 2026).
- Cause of delay — about one year, linked to a court stay on tree felling; heavy traffic limits work to off-peak hours (Construction World, 28 Oct 2026).
- Airport section — train operations on KR Puram–airport (38.44 km) targeted for November 2027 (Construction World, 28 Oct 2026).
Every opening date given in 2026
The target has moved several times. Dates are as reported; the most recent official word is the October review.
- 23 Jun 2026 — trials in October, opening likely by end-December 2026 (Public TV, 23 Jun 2026).
- 16 Aug 2026 — commercial operation in 2026 'not feasible', now expected in 2027, possibly mid-2027; pending works at Marathahalli, Silk Board, the Byappanahalli depot link and Iblur (Swarajya citing The Times of India, 16 Aug 2026).
- 19 Oct 2026 — MD PC Jaffer: trials between the Byappanahalli depot, KR Puram and Marathahalli by 15 November; opening by May 2027; about 2 km of track left; all stations except Central Silk Board to be finished by November; two trainsets delivered (OneIndia citing Moneycontrol, 19 Oct 2026).
- 23 and 28 Oct 2026 — minister's review: trials by end-October, passenger service mid-2027 (NativePlanet; Construction World).
- 8 Nov 2026 — no report of trials starting found.
What is NOT decided
- No inauguration date. Opening needs trials, signalling integration and the safety commissioner's clearance; the MD called testing speed the deciding factor (OneIndia, 19 Oct 2026).
- Whether a part-opening from KR Puram to Marathahalli happens first.
- The Silk Board end: Central Silk Board station is the last to be finished.
The 13 stations, KR Puram to Silk Board
Names as in our station file (October 2026). All are under construction; none has an opening date of its own.
- Krishnarajapura (KR Puram) — interchange with the open Purple Line
- Saraswathi Nagara
- Bagmane Developers – DRDO Sports Complex
- Doddanekundi
- ISRO
- Marathahalli — work incomplete (NativePlanet, 23 Oct 2026)
- Kadubeesanahalli
- Embassy TechVillage Devarabeesanahalli
- Prestige Bellanduru
- Ibbaluru
- Agara
- HSR Layout
- Central Silk Board — work incomplete; interchange with the open Yellow Line
Homes near the corridor
Straight-line distance from our map pin to the nearest Phase 2A station. Where our pin is a locality centre, we say so.
- Sobha Sentosa — Sobha Sentosa, Panathur side, K-RERA PRM/KA/RERA/1251/446/PR/310322/004796 to 004799, RERA completion 31 Dec 2027. About 1.9 km from Kadubeesanahalli.
- Sobha Neopolis — Sobha Neopolis, Panathur, K-RERA PRM/KA/RERA/1251/446/PR/200923/006269, RERA completion 31 Dec 2028. Locality pin, about 1.4 km from Kadubeesanahalli.
- Purva Meraki — Purva Meraki, HSR Layout, K-RERA PRM/KA/RERA/1251/310/PR/071022/005307, RERA completion 31 Oct 2027. Locality pin, about 0.8 km from HSR Layout station.
- More homes by station: Marathahalli, Bangalore and Bellandur, Bangalore.
What to do now
- 1. Plan on mid-2027 at the earliest for daily use, and on November 2027 for the KR Puram–airport section. Do not plan a 2026 move around this line.
- 2. Watch for three signals, in order: trials actually starting, the safety commissioner's inspection, and an inauguration date.
- 3. ORR road works will overlap the remaining metro work; see ORR White-Topping, Silk Board–KR Puram: ₹450 Cr Plan (2026) for the ₹450 crore white-topping plan.
- 4. For a rental or purchase decision, compare commute times from the open Purple Line at KR Puram and the Yellow Line at Silk Board today.