Updated 5 November 2026. We read the RERA Act on the HRERA website, the K-RERA quarterly-update circulars as reported, a 2025 Karnataka High Court ruling and the public registers of K-RERA, HRERA Gurugram and TNRERA as captured in our dataset on 28 October 2026.

What each RERA record proves, and what it doesn't

  • Registration certificate. Proves: the project is registered and the promoter has filed the Section 4 declarations, including the time period to complete it (Section 4(2)(l)(C)). Does not prove: quality, that the date will be met, or that every approval is final.
  • Separate account declaration. Proves: the promoter undertook to deposit 70% of amounts collected from buyers in a separate scheduled-bank account for land and construction, with withdrawals certified by an engineer, an architect and a chartered accountant (Section 4(2)(l)(D)). Does not prove: that the account balance is enough to finish; check the latest filings.
  • Quarterly update. Proves: what the promoter declared about units booked, garages booked and progress that quarter (Section 11(1)). Does not prove: that bookings are final or that the filing is current.
  • Completion date on the portal. Proves: the promoter's declared date, and any extension granted. Does not prove: possession on that date. Registration can be extended for force majeure, up to one year in total under Section 6, and regulators have issued blanket extensions; see K-RERA 4-Month Extension 2026: What It Means for Possession.
  • Occupancy certificate. Proves: the competent authority permits occupation, with water, sanitation and electricity provided for (Section 2(zf)). Issued by the planning authority, not RERA. Once issued, the buyer must take possession within two months (Section 19(10)).
  • Completion certificate. Proves: the competent authority certifies the project was built to the sanctioned plan (Section 2(q)).

Why the data can be stale or incomplete

Quarterly updates are due within 15 days of the quarter's end (K-RERA circular of 19 June 2026, as reported). Filing has not always been on time. In September 2025 the Karnataka High Court set aside K-RERA's 2020 circular that charged a delay fee for late quarterly updates and audits, holding that a fee cannot be imposed by circular (LiveLaw, 23 September 2025). K-RERA's July 2026 notification restates the duty for 2026-27 and invokes Sections 35 and 37 of the Act (TeamLease RegTech, 15 July 2026).

The safeguard is liability, not verification: a promoter who gives false information or breaks Section 4 can be fined up to 5% of the estimated project cost (Section 60), and other breaches carry up to 5% under Section 61.

How to check on each portal

A practical rule

Treat RERA as the floor of what you check, not the ceiling. Use it to confirm the registration number, the declared date, the approvals listed and the trend in bookings over four quarters. Then verify title, the OC and the bank account details independently. If a sales promise is earlier than the RERA completion date, only the RERA date and your agreement for sale bind the promoter.