The Haryana government approved a 2.25 km elevated road between Hero Honda Chowk and Umang Bhardwaj Chowk in Gurugram, and officials announced it on 1 October 2026. The Gurugram Metropolitan Development Authority (GMDA) will build it, taking over from NHAI, and the first step is a fresh detailed project report (DPR). The road is meant to improve the link between the Dwarka Expressway and the Delhi-Jaipur highway (NH-48).
Updated 3 November 2026. We re-read the approval report and the May 2026 proposal, and checked the planned metro stations on the same stretch. No construction date or contractor has been announced yet, so the dates you will see in sales material are not official.
What has been approved?
- Length: 2.25 km between Hero Honda Chowk and Umang Bhardwaj Chowk, the stretch NHAI first proposed (Swarajya, 2 October 2026).
- Approved by: the Haryana government. The decision meeting was chaired by GMDA CEO PC Meena, with chief engineer Praveen Chaudhary and NHAI officials present.
- Built by: GMDA. An NHAI official said the authority had been informed of the change.
- Next step: a new DPR. GMDA said it would appoint a consultancy firm 'within the next few days'.
- Traffic: the corridor carries 70,000 to 80,000 vehicles a day and is heavily congested at peak hours (Swarajya).
How much will the elevated road cost?
The figure you will see is ₹181 crore. It comes from NHAI's earlier proposal: a three-lane elevated section with three-lane service roads on each side at ground level, sent to the state about three months before the approval (Swarajya, 2 October 2026). In May 2026, Swarajya described the same proposal as about 3 km and about ₹181 crore, with GMDA funding all of it and NHAI building it on GMDA's behalf.
Because GMDA is now preparing a fresh DPR, the final cost, lane count and design may change. Treat ₹181 crore as the last published estimate, not the approved budget.
Where is Umang Bhardwaj Chowk, and how does it connect to Dwarka Expressway?
Hero Honda Chowk is on NH-48. Umang Bhardwaj Chowk is on the road towards Basai and the Dwarka Expressway. A 2024 Tribune report describes NHAI's earlier plan for this route: a road from Hero Honda Chowk to Shahid Umang Bhardwaj Chowk, then a flyover connecting it to the Basai flyover and on to the Dwarka Expressway. That 2024 plan was a six-lane corridor estimated at ₹138 crore.
So 'Umang Bhardwaj Chowk to Dwarka Expressway' and 'Umang Bhardwaj Chowk to Hero Honda Chowk' are two halves of one route. The October 2026 approval covers the Hero Honda Chowk half as an elevated road. The reports we opened give no new decision on the Basai side.
How has the plan changed over the years?
Swarajya's May 2026 report traces about five years of revisions. It started as road widening with a flyover at Umang Bhardwaj Chowk, then grew to include flyovers at Mohammadpur and Sector 37, and settled on the elevated-corridor model. Earlier versions mixed underpasses and flyovers. A February 2026 meeting called by Haryana Industries Minister Rao Narbir Singh with GMDA and NHAI officials restarted the push, and the minister asked that the corridor be extended to the Sector 10 bus depot.
Reported lengths differ because the scope has changed: about 3 km in May 2026 and 2.25 km in the October 2026 approval. Use the October figure.
Umang Bhardwaj Chowk news: what happened when?
- July 2024: NHAI planned a six-lane corridor from Hero Honda Chowk to Shahid Umang Bhardwaj Chowk, with a flyover to the Basai flyover, estimated at ₹138 crore (The Tribune, 11 July 2024).
- February 2026: a meeting called by Industries Minister Rao Narbir Singh with GMDA and NHAI restarted the project (Swarajya, 19 May 2026).
- May 2026: GMDA sought state clearance for an elevated road of about 3 km at about ₹181 crore, to be funded by GMDA and built by NHAI (Swarajya, 19 May 2026).
- 1 October 2026: Haryana approved a 2.25 km elevated road, with GMDA to execute it and prepare a fresh DPR (Swarajya, 2 October 2026).
- October 2026: NHAI floated an ₹81 lakh tender to repair the existing road surface (same report).
Why does this junction matter for Dwarka Expressway traffic?
The Dwarka Expressway meets NH-48 at its southern end, and traffic between the Expressway sectors and old Gurugram, Udyog Vihar and the Jaipur side passes through this belt. Swarajya puts the corridor's load at 70,000 to 80,000 vehicles a day. An elevated section lets through traffic between Hero Honda Chowk and Umang Bhardwaj Chowk pass over local junctions, while the service roads below carry local trips.
Two other works in the same part of the city are worth knowing. NHAI has cleared a ₹923 crore underground trumpet interchange on the Expressway near the Pataudi Road junction, to serve Global City and Vision City, with about 30 months of work expected (Swarajya, 7 March 2026). And on the toll side, the Bijwasan plaza is linked to Kherki Daula on NH-48, so drivers between Delhi and Gurugram are not charged twice (The Tribune).
What else is happening on this stretch?
Our reading: the road and the metro run along the same belt, so expect construction on both in the coming years. When a developer quotes a drive time to NH-48 'via the elevated road', ask for the date it assumes.
- Utilities: water, sewer and stormwater lines along the stretch are still to be shifted. High-tension power lines are being moved, and a new substation in Sector 37 will allow the existing Sector 10 substation to be relocated (Swarajya, 2 October 2026).
- Repairs: NHAI has floated an ₹81 lakh tender to repair the existing road, including relaying sections with bitumen and fixing damaged concrete (same report).
- Metro: GMRL's Phase 1 station list includes Hero Honda Chowk, Udyog Vihar Phase-6, Sector 10, Sector 37, Basai and Sector 9, with a 1.85 km spur to the Dwarka Expressway (India TV, July 2025). GMRL cast its first pile in Sector 45 in February 2026 (Indian Infrastructure).
When will the elevated road be completed?
No completion date has been published. The approval story gives no construction timeline, and the next official step is the DPR. A reliable timeline will come only when GMDA floats and awards a construction tender, which will state a build period. For comparison, GMDA's tender for the 4.23 km SPR elevated corridor sets a 30-month construction period (Construction World, 9 October 2026), but that is a different project.
For other 2026 approvals across the city, see Gurgaon Flyovers and Underpasses 2026: Approved List.
Which sectors and projects sit near this corridor?
The road links NH-48 to the old-Gurugram end of the Dwarka Expressway, so the sectors near the Expressway's southern end, including 36A and 37D, are the ones most likely to use it. These registered projects there are on our list:
- Signature Global Sarvam — Sector 37D — from ₹2.9 Cr (our listing, checked October 2026) — completion Dec 2032 — HARERA GGM/1008/740/2025/111. See Signature Global Sarvam
- BPTP The Amaario — Sector 37D — price on request (no builder price published) — completion Sep 2031 — HARERA GGM/820/552/2024/47. See BPTP The Amaario
- Krisumi Waterside Residences — Sector 36A — from ₹4.35 Cr (developer price list; our listing, checked October 2026) — completion Oct 2029 — HARERA GGM/812/544/2024/39. See Krisumi Waterside Residences
- Max Estate 361 — Sector 36A — 3 BHK from ₹6.65 Cr (developer page; our listing, checked October 2026) — completion Sep 2033 — HARERA GGM/1012/744/2025/115. See Max Estate 361
Sector pages: Sector 37d Gurgaon, Gurgaon and Sector 36a Gurgaon, Gurgaon. For the sector itself, read Sector 37D Gurgaon Projects 2026: Prices, Elevated Road, and for the neighbouring sector, Sector 37C Gurgaon: Buyer's Guide 2026 — Prices, Projects and Connectivity.
What should buyers check?
- Whether a project's brochure quotes drive times that assume the elevated road. If it does, ask for the date assumed and note that there is no official one yet.
- The HARERA completion date of the project, which does not depend on road works.
- Your daily route: if you cross Bijwasan or Kherki Daula, add the toll pass to your running costs (see Dwarka Expressway Toll Pass 2026: Annual Pass, Rules).
- GMDA's tender notices for this road, which will give the length, lanes and build period once the DPR is done.