Updated 5 November 2026. We searched again for news after 25 October and found no reply from the Centre, no AAI pre-feasibility report and no site decision; the 25 October report remains the latest dated step. New below: the figures that published reports disagree on (dates, distances, acreage), shown side by side with their sources, and what is known about land at Cheyyur and at Parandur. Earlier guide: Parandur Airport Status and Chennai Peripheral Ring Road (2026).

Chennai second airport status on 5 November 2026

  • Parandur: dropped. Announced by the Chief Minister in the Assembly on 24 August 2026; AAI informed (DT Next, 7 October 2026).
  • Shortlist: Cheyyur (Chengalpattu district) and Manellore near Gummidipoondi (Tiruvallur district). Not selected or notified (DT Next, 7 October 2026).
  • AAI step: the state asked AAI for a pre-feasibility study of both sites; a report was expected 'within the next few months' (Republic, 6 September 2026). No result reported as of 5 November 2026.
  • State's letters: still awaiting the Centre's reply as of 25 October 2026 (The Hindu, via the Verified.RealEstate tracker).
  • Timeline once a site is fixed: officials estimate at least five to seven years to build (Republic, 6 September 2026).
  • Existing airport: AAI has proposed a satellite terminal inside the present airport premises with capacity for another 20 million passengers a year (Swarajya, citing Times of India, 17 September 2026). See Chennai Airport Expansion 2026: Terminal 5 and the 217 Acres.

Where the reports disagree: dates, distances and acreage

Several figures differ between outlets. We show each version with its source rather than pick one:

  • Shortlist date: 5 September 2026 (The Hindu, via the Verified.RealEstate tracker) or 6 September 2026 (Indian Aviation News and Republic, both published 6 September). None of them cites an official order.
  • Parandur decision: 24 August 2026 in the Assembly (DT Next, 7 October 2026). The Hindu reported on 23 August that the state planned to explore alternative sites (via the Verified.RealEstate tracker).
  • Cheyyur distance from Chennai: about 90 km (an official quoted by Times of India, via Swarajya, 17 September 2026) or about 100 km (Indian Aviation News, 6 September; Republic gives 100 km from Meenambakkam airport).
  • Manellore distance from Chennai: about 50 km from the city (Republic, 6 September) or about 60 km (Indian Aviation News, 6 September).
  • Parandur project area: 5,746 acres (DT Next, 12 September 2026), 5,747 acres across 13 villages (Indian Aviation News, citing India Today) or about 5,846 acres (Aviation A2Z, 5 October; Republic, 6 September).
  • Parandur land acquired: about 1,802 acres (Aviation A2Z; Swarajya, citing Times of India, which gives 1,802 of 3,874 acres of patta land identified) or nearly 1,700 acres (DT Next, 12 September 2026).

What land is available at Cheyyur, and what happens to Parandur's?

At Cheyyur, the government already holds 623 acres acquired earlier for a Union government power project through the Tamil Nadu Power Finance Corporation, and about 300 acres of poramboke land is also available, according to government sources quoted by Times of India (via Swarajya, 17 September 2026). Republic (6 September) reported that Cheyyur may need Ministry of Defence clearance because it lies in airspace controlled by the Indian Air Force station at Tambaram, and that a TIDCO team had completed initial inspections of both sites.

At Parandur, a land acquisition official said on 12 September that the government 'has not yet made any decision on repurposing the land', and Industries Department sources said it could be used for non-polluting industry (DT Next). Republic (6 September) said the acquired land was expected to be used for industrial purposes; Swarajya (17 September) said the government was examining options to return it to the original owners. We found no decision on either as of 5 November 2026.

Chennai second airport timeline, August to October 2026

  • 24 August: Chief Minister C Joseph Vijay told the Assembly the Parandur project would be abandoned, citing agricultural land, waterbodies, flooding and the impact on residents (DT Next, 7 October 2026).
  • Before the decision, about 1,802 of the roughly 5,846 acres needed at Parandur had been acquired, and the project was costed at about ₹27,400 crore (Aviation A2Z, 5 October 2026).
  • 25 August: Andhra Pradesh minister Nara Lokesh said a Sri City airport proposal is not under consideration (NDTV, via Verified.RealEstate).
  • 5 September: Tamil Nadu shortlisted Cheyyur and Gummidipoondi (The Hindu, via Verified.RealEstate).
  • 16 to 17 September: reports said the state was focusing on Cheyyur, and that it had emerged as the likely site (Times of India; Swarajya; both via Verified.RealEstate). Neither is an official selection.
  • 7 October: TIDCO's RTI reply confirmed Parandur was dropped, that AAI had been informed, and that preliminary technical and field studies had begun, with no site confirmed (DT Next).
  • 25 October: the state was awaiting the Centre's reply to two letters, one from August asking that AAI be replaced as operator of the existing airport, and one from September seeking a pre-feasibility study on Gummidipoondi and Cheyyur (The Hindu, via Verified.RealEstate).

Where are Cheyyur and Gummidipoondi?

Cheyyur is south of Chennai in Chengalpattu district, inland from the East Coast Road beyond Mamallapuram. Manellore is near Gummidipoondi in Tiruvallur district, in the north on the Chennai–Kolkata highway towards the Andhra Pradesh border (district names from DT Next, 7 October 2026). They pull in opposite directions: one would favour the southern ECR and GST belt, the other the northern industrial corridor.

AAI had earlier assessed Parandur, Pannur, Padalam and Thiruporur before Parandur was chosen (DT Next, 7 October 2026), which shows how long a site decision can take even after a shortlist.

What happens next, and how long could it take?

The next formal step is a pre-feasibility study, which depends on the Centre's response. After that would come site selection, approvals and land acquisition. No authority has published a timeline or cost for either site. The only estimate we found is officials' 'at least five to seven years' to build once a site is fixed (Republic, 6 September 2026), so anyone quoting an opening year for a Cheyyur or Gummidipoondi airport is guessing.

Meanwhile the existing airport is where near-term change is happening: a Terminal 5 was announced on 25 August 2026 and is at the planning stage (Verified.RealEstate tracker); see also Chennai Airport New Terminal Opening Date: Now April 2027 for the new terminal timeline.

Should you buy plots near Cheyyur or Gummidipoondi now?

Not on the airport alone. Parandur shows the risk: land around it was marketed on the airport for years, and the project was dropped with less than a third of the land acquired (our arithmetic from Aviation A2Z's figures: 1,802 ÷ 5,846 ≈ 31%). A shortlist is not a decision.

  • Buy only what makes sense without the airport: present road access, jobs within commuting range and a clear DTCP- or CMDA-approved layout.
  • Be wary of layouts advertised as 'airport-facing' or 'next to the new airport'; no site is notified.
  • If the airport does come, land inside the eventual acquisition boundary is acquired, not sold at a premium. Proximity is not always a gain.
  • Check TNRERA registration for layouts and verify approval on the DTCP or CMDA site.

What about land around Parandur?

With the project withdrawn, the reason most buyers paid a premium there has gone. We have no reliable price data for the Parandur belt after August 2026 and will not guess. Owners deciding whether to hold or sell should look at what the land is useful for today, its zoning and its road access.