The 3.6 km Red Line link from Chennai Trade Centre (Nandambakkam) to Alandur, mostly along Butt Road, was given 45 to 60 more days of work in early September 2026 (Construction World, 8 September). That window closed by early November without a reported completion. The latest update (LiveChennai, 4 November 2026) says remaining viaduct and track work on Koyambedu–Alandur is aimed for December 2026, with passenger service targeted for March 2027.
Updated 8 November 2026. We checked the September and November reports and CMRL's press-release list. This link decides whether the first Red Line section ends at Trade Centre or reaches the Alandur interchange with the Blue and Green Lines.
Timeline of the Alandur link
- 5 September 2026: LiveChennai reported that the 3.6 km Nandambakkam–Alandur connection still needed 45 to 60 days, and that full Koyambedu–Alandur service was expected next year.
- 8 September 2026: Construction World reported that CMRL's board was discussing running the first section through to Alandur; the Alandur–Trade Centre link, largely along Butt Road, could take 45 to 60 more days; Koyambedu–Alandur was unlikely to open before 2027 and could be commissioned in the first quarter.
- Late October to early November 2026: the 45 to 60 days counted from early September ran out. We found no report that the link was complete.
- 4 November 2026: LiveChennai said entry and exit facilities at Butt Road and at the Alandur Phase 2 station are a major challenge; Alandur will be an interchange with the Phase 1 network; trial runs are likely in January 2027 and passenger service is targeted for March 2027.
Stations on the link
- Chennai Trade Centre (Nandambakkam): end of the first-planned Koyambedu section.
- Butt Road: intermediate station; entry and exit work flagged as a challenge (LiveChennai, 4 November 2026).
- Arignar Anna Alandur: Phase 2 Red Line station, to interchange with the existing Blue and Green Lines at Alandur.
- Beyond Alandur, the Red Line continues to St Thomas Mount and on towards Sholinganallur; that section has its own schedule (Sholinganallur Metro Opening Date: Corridor 5 Status, Oct 2026).
Dates for these stations: which source says what
- LiveChennai, 4 November 2026: Koyambedu–Alandur passenger service targeted for March 2027, trial runs likely in January 2027. This is the most recent report we found.
- Construction World, 8 September 2026: Koyambedu–Alandur unlikely before 2027, possibly in the first quarter.
- Wikipedia's Red Line table (read 8 November 2026): June 2027 for Chennai Trade Centre, Butt Road and Alandur. That table cites a January 2024 report in The Hindu, so it is older than both news reports above.
- CMRL: no announced date. Its press releases up to 2 November 2026 do not cover this section's opening.
Alandur today
Alandur (Arignar Anna Alandur) is already a working interchange between the Blue Line (Wimco Nagar Depot to the airport) and the Green Line (Chennai Central to St Thomas Mount), both open end to end. The Phase 2 Red Line station is a separate structure that will connect to it. Until it opens, residents of Manapakkam and Nandambakkam reach Alandur, Guindy or St Thomas Mount by road; Guindy and St Thomas Mount are the nearest working metro stations on the south side.
Why Alandur matters for buyers
Without the link, the first Red Line section would end at Trade Centre, short of the Phase 1 network. With it, residents along Valasaravakkam, Ramapuram and Manapakkam could change at Alandur for the airport (Blue Line) or Central (Green Line). That is why the reports treat the Alandur extension as part of the first opening.
TNRERA-registered projects in our catalogue near the south end of the section (by locality; check the walk on site):
- Manapakkam: L&T Avinya Enclave Phase 2, TNRERA/29/BLG/0086/2026 (L&T Avinya Enclave Phase 2); TVS Emerald Peninsula, TN/29/Building/0032/2021 (TVS Emerald Peninsula).
- Nandambakkam: Isha River Front, TNRERA/29/BLG/0094/2026 (Isha River Front).
- Guindy: VGN Richmond Towers, TN/29/Building/0549/2024 (VGN Richmond Towers); Purva Somerset House, TN/29/Building/013/2019 (Purva Somerset House).
What is not decided yet
- Whether the first passenger section opens to Alandur or stops at Trade Centre. The September report described this as under discussion by CMRL's board; the November report treats Koyambedu–Alandur as one opening.
- Any official opening date. March 2027 is a reported target.
- Completion of station entries and exits at Butt Road and Alandur.
What to do now
- 1. Read any '45 days' claim with its date: it was given in early September 2026 and has lapsed.
- 2. If you are buying in Manapakkam, Ramapuram or Guindy for an Alandur interchange, assume no Red Line service before March 2027 and possibly later.
- 3. Compare projects at Manapakkam, Chennai and Guindy, Chennai, and check each TNRERA completion date on tnrera.in.
- 4. Follow the trial-run status at Koyambedu–Trade Centre Metro Trial Run: Now January 2027.