Global City's published plan is a roughly 1,000-acre mixed-use township in Sectors 36, 36B, 37, 37A and 37B with its first phase targeted for the end of 2026 and full build-out expected through 2035 (The Tribune, 31 July 2026). Its access plan has four parts: a ₹923 crore NHAI underground interchange on Dwarka Expressway, a new arterial road to NH-48, Pataudi Road links to Manesar and KMP, and a metro feasibility study through the area.
Updated 7 November 2026. This update covers the master plan's roads and transit with dates and stage. For history, the auction notice and the tower plan, see our 13 October post: Global City Gurgaon 2026: Status, Master Plan and Nearby Sectors. We found no HSIIDC master-plan document online and no newer official status after August 2026.
Global City master plan at a glance
- Land: about 1,000 acres (The Tribune); Swarajya gives over 1,003 acres across Sectors 36, 36B, 37 and 37B (7 March 2026).
- Developer of infrastructure: HSIIDC, which auctions land to private developers.
- Use: mixed-use, positioned as NCR's central business district (The Tribune, 31 July 2026).
- Jobs: more than five lakh once fully operational, per The Tribune's report.
- Investment potential: about ₹1 lakh crore across all stages (The Tribune).
- Tower plan: a 6.7-acre plot identified for a proposed 620–700 metre mixed-use tower (The Tribune).
Roads and transit in the plan: dated list
- Dwarka Expressway interchange: a four-lane underground trumpet interchange near the Pataudi Road junction on NH-248BB, about 30 feet below ground with 3.2 km of ramps; NHAI to build it, HSIIDC to fund about ₹923 crore; cleared, about 30 months of work once started (Swarajya, 7 March 2026). It also serves Vision City, 121 acres in Sector 88.
- NH-48 link: a new wide arterial road near Narsinghpur to connect directly to NH-48 (The Tribune, 31 July 2026). No cost or date published.
- Manesar and KMP: Pataudi Road to connect the township to Manesar and the KMP Expressway (The Tribune).
- Metro study: RITES is studying an MG Road–Sector 95 corridor with reported stops at Global City, Vision City (Sector 88), Sector 92 and Sector 95 (Swarajya, 23 June 2026). Feasibility stage only.
- Metro spur: the revised ₹10,266 crore Millennium City Centre–Cyber City metro includes a spur at Dwarka Expressway (Indian Infrastructure, 19 May 2026).
Global City timeline: what the dates mean
- 2019: project announced; it then stalled until a 2023 relaunch (The Tribune).
- 2025: first-phase work began.
- End of 2026: first-phase infrastructure target.
- Through 2035: expected full build-out (The Tribune). This is the first dated horizon we have seen from a major newspaper; buildings arrive developer by developer.
Collector rates around Global City, 2026-27
- Plots, Sectors 33, 34, 35, 36, 37, 37A (Kadipur): ₹66,000 → ₹85,800 per sq yd (+30%); Sector 37 listed separately at ₹75,900 (+15%).
- Plots, Sectors 37C and 37D: ₹66,000 → ₹85,800 per sq yd; flats ₹6,000 → ₹6,500 per sq ft.
- Flats, Sector 36A: ₹7,700 → ₹8,500 per sq ft (Manesar tehsil list) and ₹6,500 → ₹7,000 (Harsaru list).
What the plan means for buyers nearby
ANAROCK names Global City, the Gurugram metro extension and UER-II as future drivers for Dwarka Expressway (Outlook Money, 9 September 2026). It gives no price effect, and we found no study that measures one.
- Homes near Global City are in Sectors 36A, 37C, 37D and the Sector 88 belt, not inside the township, which HSIIDC sells to developers by auction.
- A RERA-registered example nearby: Signature Global De Luxe DXP, Sector 37D, RC/REP/HARERA/GGM/783/515/2024/10, completion listed Mar 2031. See Signature Global De Luxe DXP
- Corridor data and drivers: Dwarka Expressway Investment 2027: Drivers With Dates; sector detail: Sector 37D Gurgaon Projects 2026: Prices, Elevated Road