Updated 7 November 2026. We read every row of HARERA Gurugram's registered-projects list and its 'Registration Up-to' column, which is the registered completion date, and opened the OC/CC record behind each row that has one. Commercial registrations are left out. For the whole of 2027 by quarter, see Gurgaon Possession Jan-Mar 2027: 36 HRERA Dates (Q1)

December 2026 HRERA dates on Dwarka Expressway and New Gurgaon

  • The Millennia-IV, Sector 37D: 30 Dec 2026, HRERA GGM/518/250/2021/86.
  • M3M Capital Phase 2, Sector 113: 31 Dec 2026, HRERA GGM/612/344/2022/87. OC record dated 26 May 2026. Project page: M3M Capital
  • Sobha City Phase 5, Sector 108: 31 Dec 2026, HRERA GGM/410/142/2020/26. Project page: Sobha City
  • Zara Aavaas-3, Sector 104: 31 Dec 2026, HRERA GGM/464/196/2021/32.
  • Signature Global City 92-(1), Sector 92: 28 Dec 2026, HRERA GGM/471/203/2021/39.
  • Signature Global Superbia, Sector 95: 29 Dec 2026, HRERA GGM/426/158/2020/42.
  • 8.7111-acre DDJAY plotted colony by Loon Land Development, Sector 79: 30 Dec 2026, HRERA GGM/649/381/2022/124.
  • M3M Antalya Hills Phase 1, Sector 79: 30 Dec 2026, HRERA GGM/650/382/2022/125.
  • JMS Premier Floors, Sector 95: 31 Dec 2026, HRERA GGM/801/533/2024/28. OC records dated 17 Jun 2025 and 9 Jun 2026.
  • JMS Premier Floors-II, Sector 95: 31 Dec 2026, HRERA GGM/895/627/2024/122. OC record dated 9 Jun 2026.
  • JMS The Nation, Sector 95: two registrations, both 31 Dec 2026, HRERA GGM/692/424/2023/36 and GGM/745/477/2023/89.
  • Mahira Homes 88B, Sector 88B: 31 Dec 2026, HRERA GGM/707/439/2023/51.
  • Signature Global City 79B-1, Sector 79B: 31 Dec 2026, HRERA GGM/659/391/2023/03.
  • Signature Global City 92-2, Sector 92: 31 Dec 2026, HRERA GGM/665/397/2023/09.
  • SS Linden, Sectors 84-85: 31 Dec 2026, HRERA GGM/497/229/2021/65.
  • Whiteland Arena 76, Sector 76: 31 Dec 2026, HRERA GGM/644/376/2022/119.

December 2026 HRERA dates on SPR, Golf Course Extension Road and central Gurugram

  • Grand Vista by Pyramid Infratech, Sector 73: 15 Dec 2026, HRERA GGM/560/292/2022/35. OC record dated 3 Dec 2025.
  • Imperial Estate by Pyramid Infratech, Sector 70A: 20 Dec 2026, HRERA GGM/559/291/2022/34. OC/CC record dated 16 Dec 2024.
  • The Residences Three Sixty, Sector 70A: 30 Dec 2026, HRERA GGM/890/622/2024/117.
  • South Drive, Sector 69: 31 Dec 2026, HRERA GGM/778/510/2024/05.
  • Ashok Estate by Anant Raj, Sector 63A: 31 Dec 2026, HRERA GGM/589/321/2022/64.
  • Birla Navya (Anaika), Sector 63A: 31 Dec 2026, HRERA GGM/596/328/2022/71. Project page: Birla Navya
  • Marbella Phase 7 by Emaar India, Sector 66: 31 Dec 2026, HRERA GGM/1080/812/2026/52 (registered 5 Aug 2026).
  • Samsara Avasa, Sector 63: 31 Dec 2026, HRERA GGM/648/380/2022/123. OC record dated 6 Oct 2025.
  • Samsara Vilasa and Samsara Arya, Sector 32: 31 Dec 2026, HRERA GGM/647/379/2022/122. OC record dated 6 Oct 2025.
  • Orchid Ivy and Orchid Ivy-2, Sector 51: both 31 Dec 2026, HRERA GGM/597/329/2022/72 and GGM/646/378/2022/121.

December 2026 HRERA dates in Sohna and IMT Manesar

  • Central Park Flower Valley Phase III, Sectors 29, 30, 32 and 33 Sohna: 9 Dec 2026, HRERA GGM/562/294/2022/37.
  • Bonheur Avenue, Sector 35 Sohna: 31 Dec 2026, HRERA GGM/606/338/2022/81. CC record dated 18 Jun 2024.
  • Bonheur Avenue Grow+, Sector 35 Sohna: 31 Dec 2026, HRERA GGM/725/457/2023/69.
  • Express Greens by HSIIDC, IMT Manesar Sectors M1 and M1A: both 31 Dec 2026, HRERA GGM/608/340/2022/83 and GGM/609/341/2022/84.

Which December 2026 projects already show an OC or CC on HRERA?

Eight of the 33 rows have an OC or CC record behind the 'View OC/CC/PCC' link: M3M Capital Phase 2, JMS Premier Floors, JMS Premier Floors-II, Grand Vista, Imperial Estate, Samsara Avasa, Samsara Vilasa and Arya, and Bonheur Avenue. The dates are in the lists above.

A completion date on the register and an OC are different things. The registered date is the end of the registration period the promoter declared; an OC can be issued before it. An OC can also cover only some towers, so ask for the copy that names your tower. All 30 Gurgaon registrations in the 2026-27 window with an OC or CC record are in Ready to Move in Gurgaon: 30 HRERA Rows With OC or CC (2026)

What does a December 2026 HRERA date mean for a buyer?

How do I check a project's December 2026 date myself?

  • Open the HRERA Gurugram 'Registered Projects' list on haryanarera.gov.in.
  • Search the registration number from this page, for example GGM/612/344/2022/87.
  • Read 'Registration Up-to' for the date, and click 'View OC/CC/PCC' for any certificate uploaded.
  • Match the promoter name on the row with the company named in your agreement. Many projects are registered by a group company.