The Millennium City Centre–Cyber City metro is a 28.5 km elevated loop with 27 stations, at a revised cost of ₹10,266 crore approved in May 2026 (ThePrint, 18 May 2026). Phase 1, from Millennium City Centre to Sector 9 with a spur to Sector 101, had reached about 15% physical progress by early October 2026. Phase 2, from Sector 9 through Old Gurgaon to Cyber City, has a ₹1,662 crore civil tender with bids due 9 to 18 November 2026 (Swarajya, 6 October 2026).
Updated 5 November 2026. We added a station-by-station tracker built from the Phase 2 tender, the Phase 1 route release and ThePrint's cost-revision report, and re-checked the progress figures. GMRL does not publish progress station by station, so the status below is given for each phase. Buyers in Gurgaon hear about the metro constantly, but the reality is a mix of an existing Rapid Metro loop, a new corridor under construction and several proposals; this guide separates the three and says plainly where reports disagree.
Gurugram metro station-by-station status tracker (5 November 2026)
Phase 1: Millennium City Centre to Sector 9, plus spur. Status: under construction since the first pile in February 2026; about 15% physical progress in early October 2026 (Swarajya, 6 October 2026). India TV named 13 of its stations in July 2025; Swarajya counts 14 for Phase 1.
- Millennium City Centre: existing Yellow Line terminus; planned interchange
- Sector 45 (first pile cast here, 12 February 2026)
- Cyber Park (Sector 46)
- Sector 47
- Subhash Chowk: planned interchange
- Sector 48
- Sector 33: a depot of 22.86 hectares is planned in this sector (ThePrint, 18 May 2026)
- Hero Honda Chowk: planned interchange; also a proposed Namo Bharat station
- Udyog Vihar Phase 6
- Sector 10
- Sector 37
- Basai
- Sector 9: end of Phase 1 and start of Phase 2
- Sector 101: on the 1.85 km spur towards Dwarka Expressway (India TV, 7 July 2025)
Phase 2: Sector 9 to Cyber City, 14.2 km, 13 stations. Status: ₹1,662 crore civil tender floated on 6 October 2026, bids 9 to 18 November 2026, 30 months to build after award (Swarajya, 6 October 2026). Stations in order from Sector 9:
- Sector 7
- Sector 4
- Sector 5: planned interchange; a 1.8 km spur to Gurugram Railway Station is to start here
- Ashok Vihar
- Sector 3
- Bajghera Road: about 800 m of double-decker road-and-metro structure at Bajghera
- Palam Vihar Extension
- Palam Vihar
- Sector 23A
- Sector 22
- Udyog Vihar Phase 4
- Udyog Vihar Phase 5
- Cyber City: planned interchange with the Rapid Metro and the proposed Namo Bharat station
Railway station spur: 1.8 km from Sector 5 to Gurugram Railway Station, costed at ₹454.32 crore within the revised project cost (ThePrint, 18 May 2026). We found no separate tender for it as of 5 November 2026.
Two progress figures are in circulation. UNI reported 3.3% physical progress as of June 2026, citing a Rajya Sabha reply; Swarajya reported about 15% for Phase 1 on 6 October 2026. They are four months apart and may not measure the same scope, so we show both. Interchange locations are from Swarajya (29 July 2026); station names on any line can still change until the final drawings are public.
Planning note: the stretch from Subhash Chowk to Cyber City via Hero Honda Chowk, Basai, Sector 4, Ashok Vihar, Palam Vihar and Udyog Vihar Phase 4 was added to Haryana's transit-oriented development (TOD) corridors by a gazette amendment of 4 October 2021, so land along it can qualify for higher FAR under that policy. How TOD works: TOD Zone Gurugram 2026: 1.5 km Namo Bharat Rules for Buyers.
What runs today
The existing Rapid Metro runs largely along Golf Course Road and Golf Course Extension Road, with Sector 55-56 as its southern terminus and a Sikanderpur interchange with the Delhi Metro Yellow Line (Square Yards, 14 August 2026). Frequency is every five to seven minutes through most of the day. It runs through the Cyber City and Golf Course Road belt; check the nearest station for any specific address.
The new corridor: scope and cost
The Millennium City Centre-Cyber City project is being implemented by Gurugram Metro Rail Limited (GMRL). Indian Infrastructure reports it as a 30.5 km route from Millennium City Centre to Udyog Vihar Phase 5, merging with the Rapid Metro at Moulsari Avenue near Cyber City, with spurs to the Dwarka Expressway and Gurugram railway station. Other reports quote 28.5 km, which appears to exclude the added railway-station spur. The Tribune reports a 28.5 km corridor with 35 three-coach trains.
Cost has moved. Swarajya reports the original cost at ₹5,452.72 crore. The Tribune says it now exceeds ₹8,000 crore, with delays adding over ₹3,000 crore. On 19 May 2026 the Haryana government approved a revised cost of ₹10,266 crore (Rs 102.66 billion), per Indian Infrastructure, including a 1.8 km spur from Sector 5 to Gurugram railway station.
Where construction stands
- First pile cast on 12 February 2026 in Sector 45 (Indian Infrastructure).
- Initial work from Millennium City Centre to Sector 9 involves about 3,000 piles and around 750 pillars (Indian Infrastructure).
- Physical progress was 3.3% as of June 2026 (UNI), and about 15% for Phase 1 by early October 2026 (Swarajya, 6 October 2026).
- Civil tenders had been finalised for about 15 km, with the remaining 13 km to follow, according to the Tribune.
- Phase 2 (Sector 9 to Cyber City): land was identified in Sectors 7, 4, 5, 3, Ashok Vihar, Bajghera, Palam Vihar Extension, Palam Vihar and Sector 23A (Indian Infrastructure, 27 January 2026). Its ₹1,662 crore civil tender, World Bank-funded, was floated on 6 October 2026 with bids due 9 to 18 November (Swarajya, 6 October 2026).
- Depot: planned in Sector 33. Reports differ on size: about 45 acres in earlier coverage, 22.86 hectares (about 56 acres) of government land in ThePrint's 18 May 2026 report.
- Funding: the European Investment Bank never confirmed its share, so the World Bank will now fund the whole soft-loan portion (ThePrint, 18 May 2026).
Which sectors and stations
Swarajya lists these names along the corridor: Subhash Chowk, Hero Honda Chowk, Udyog Vihar Phases 4-6, Basai Village, Sector 5, Sector 3, Palam Vihar Extension, Palam Vihar and Sector 101, with Millennium City Centre and Cyber City as connection points and 27 stations in all. Interchange stations are planned at Millennium City Centre (Yellow Line), Subhash Chowk, Sector 5, Hero Honda Chowk and DLF Cyber City (Swarajya, 29 July 2026). Double-decker stretches are proposed near Krishna Chowk and Sector 21.
In plain terms, localities such as Palam Vihar, Sector 21, Udyog Vihar, Sector 5 and Subhash Chowk are the ones the new line is designed to serve. Exact station locations may change, so confirm against the latest alignment before relying on a walking distance.
The timeline and why to be cautious
The Tribune and ThePrint (18 May 2026) give a target completion of December 2028; Swarajya reported a 2028 target for Phase 1 when on-ground work began (28 November 2025), and Phase 2's 30-month contract cannot finish before 2029 if awarded in early 2027 (our reading). Other coverage points to 2029. One report says the 2023 approval assumed a four-year schedule, and the added spur and delays have pushed it out. At 3.3% progress in mid-2026, any date is a target, not a promise. Our advice: treat the line as a multi-year benefit and avoid paying today for a service that will not run for some time.
Extensions and proposals
- Sector 56 to Panchgaon: a proposed 36 km line with 28 elevated stations serving Nirvana Country, Vatika Chowk, Kherki Daula, Global City and Manesar. The DPR by RITES was submitted to the state on 16 May 2026, pending approval, at about ₹10,000 crore (Swarajya).
- Sector 56 hub: GMDA's CEO proposed on 7 January 2026 that Sector 56 become a multi-modal hub where the Rapid Metro, the Panchgaon line and the planned Sector 5 line converge (Swarajya, 8 January 2026).
- Dwarka Expressway: the new corridor includes a 1.85 km spur at the Basai village end towards the Dwarka Expressway (Swarajya). For expressway property context see our Dwarka Expressway guide.
What this means for buyers
- Palam Vihar and other west-Gurgaon pockets stand to gain, but not before the second phase is built.
- Do not assume resale values will rise when stations are announced; price paths depend on supply, demand and interest rates as much as transit.
- Check any plot or floor against the metro alignment and land acquisition notices; GMRL has issued public notices to acquire private land (Swarajya).
- For ready homes near the Rapid Metro, confirm the walking route and the station distance yourself.