On the STRR road map, about 80 km of Bengaluru's Satellite Town Ring Road, from Dobbaspet through Doddaballapur and Devanahalli to Hoskote, has been open and tolled since 2024. The next link, the 21 km Hoskote–Hosur (Tamil Nadu border) stretch, is not open yet: NHAI is working towards a phased opening by December 2026, with traffic diverted around the railway overbridge at Lingadeeramallasandra, whose second girder is expected by March 2027 (Oneindia, 23 October 2026). The western and southern arc, through Magadi, Ramanagara, Kanakapura and Anekal, has not been awarded and is further out.
Updated 5 November 2026. We searched again for news after 23 October and found no report that the Hoskote–Hosur stretch has opened or that the first girder has been launched. December 2026 for a phased opening and March 2027 for the second girder remain the latest targets (Oneindia, 23 October 2026). We also corrected the western arc. NHAI cancelled the five packages it tendered in September 2024 and split the section into two packages for a fresh tender (Urban Acres, 15 October 2025). Our stretch-level explainer is STRR Hoskote–Hosur Stretch: Opening by December 2026?. Homes listed near the open eastern half include Prestige Parklane, Sattva Ekatra (plots), Sattva Aangané and, at the Hosur end, Sobha Hamptons Townpark Phase 2.
What is the STRR and where does it run?
The STRR is an access-controlled highway, notified as NH-948A, being built by the National Highways Authority of India (NHAI) to circle Bengaluru at a distance, linking the satellite towns around the city and letting long-distance trucks bypass it. Deccan Herald describes it as a 288 km, ₹17,000 crore project, with 243 km in Karnataka and 45 km in Tamil Nadu.
Read as a map, clockwise from the north-west, the planned ring runs: Dobbaspet, Doddaballapur, Devanahalli, Hoskote, the Tamil Nadu section near Hosur, back into Karnataka near Anekal, then Thattekere (Kanakapura taluk), Kunigal side (Ramanagara taluk), Magadi, and Obalapura near Nelamangala, closing at Dobbaspet. The eastern half is the one being built first.
What is the STRR's current status, section by section?
- Open: Dobbaspet to Doddaballapur bypass (42 km) and Doddaballapur bypass to Hoskote (37.6 km), together roughly 80 km, inaugurated on 11 March 2024. Tolling on the Doddaballapur–Hoskote part began in November 2023.
- Nearly complete: Hoskote to the Tamil Nadu border, 20.9 km. Deccan Herald reported on 25 July 2026 that NHAI said over 95% of the work was done, and that the railway had approved the drawings for two 54-metre bowstring girders over the Bengaluru–Chennai line near Hoskote, with a final railway inspection still to come. In October 2026 NHAI said the Research Designs and Standards Organisation (RDSO) had inspected the site, its observations had been addressed and a fresh inspection was expected; NHAI is exploring a phased opening by December 2026, and the girder for the Hoskote-bound carriageway is expected by March 2027 (Oneindia, 23 October 2026).
- Under construction: the Tamil Nadu section, reported at over 91% complete in August 2026 and targeted for September 2026 (Times of India, via Swarajya). We found no later report on whether that target was met.
- Not yet awarded: the 144.25 km western and southern arc. NHAI put five packages out to bid in September 2024 at ₹4,749.74 crore. It cancelled them in January 2025, citing delays in land acquisition and approvals, and repackaged the section into two: Obalapura (Nelamangala) to Kunigal, and Kunigal to S Mudugadapalli (Hosur). Fresh tenders were invited, but the Centre paused several Bharatmala highway works, including the STRR (Urban Acres, 15 October 2025). We found no report of an award as of 5 November 2026.
- Hardest stretch: 8.34 km through Bannerghatta National Park between Thattekere and Bagganadoddi, designed with wildlife underpasses at about ₹122 crore per km. In 2024 NHAI said wildlife board clearance had been received but forest and environmental clearances were still awaited.
When will the STRR be completed?
There is no single completion date for the full ring; NHAI gives targets section by section, and the railway overbridge near Hoskote sets the pace for the next link.
The latest target for the Hoskote–Hosur stretch is a phased opening by December 2026, with overbridge work continuing to March 2027 (Oneindia, 23 October 2026). In August the Times of India reported a target of about 144 km operating continuously from Dobbaspet to Hosur, a section it put at ₹14,655 crore. When the Hoskote–border stretch opens, NHAI has said the STRR's operational length rises to 102.6 km. For the full 288 km ring, we found no credible current completion date; the western packages were given two years from award, and the Bannerghatta section depends on clearances.
A sensible working assumption for buyers: the eastern half (Dobbaspet to Hosur) is a 2026–27 reality; the western and southern arc is a late-decade possibility.
STRR map: the five western and southern packages
These are the packages NHAI tendered in September 2024, as listed by Deccan Herald. Those tenders were cancelled in January 2025, and the section was split into two larger packages, Obalapura to Kunigal and Kunigal to S Mudugadapalli (Urban Acres, 15 October 2025). The 2024 list still shows where the road is planned. It is also the list most often cited in plot marketing, so it helps to know exactly where each stretch runs.
- Obalapura (Nelamangala taluk) to Somakkanamutta (Magadi taluk): 46.30 km, ₹1,419.90 crore.
- Somakkanamutta (Magadi taluk) to Kunagal (Ramanagara taluk): 32.7 km, ₹825.19 crore.
- Kunagal (Ramanagara taluk) to Thattekere (Kanakapura taluk): 33.64 km, ₹978.91 crore.
- Thattekere (Kanakapura taluk) to Bagganadoddi (Anekal taluk), through Bannerghatta National Park: 8.34 km, ₹1,018.35 crore.
- Bagganadoddi (Anekal taluk) to S Muduganapalli (Hosur taluk): 23.27 km, ₹507.39 crore.
Why does the Hoskote to Hosur stretch matter?
It is the link that turns the STRR from a north-east bypass into a useful arc. NHAI says the Hoskote–border stretch will connect to the Bengaluru–Chennai Expressway and help decongest Old Madras Road and Sarjapur Road. For freight between the airport side, Hoskote's industrial belt and Hosur, it removes the need to enter the city.
For homebuyers, the benefit is mostly indirect: better freight and commuter flows on the eastern fringe, and easier access between Hoskote, the airport corridor and Hosur. Our Hoskote guide is at Hoskote, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks
Is there a toll on the STRR?
Yes. When tolling began on the Doddaballapur–Hoskote section in November 2023, Deccan Herald reported ₹70 for a single car trip and ₹105 for a return within 24 hours, collected at the Nalluru toll plaza near Devanahalli, with two-wheelers exempt. Those were the initial notified rates; toll rates are revised periodically, so check the current figure on NHAI's toll information before relying on it.
Which satellite towns gain from the STRR, and which are still hype?
- Real now: Doddaballapur, Devanahalli and Hoskote, on the open 80 km. The road already exists; any benefit is visible and partly priced. Devanahalli's market is driven mainly by the airport. See Doddaballapur Road, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks
- Near-term: the Hoskote–Hosur side, once the border stretch and Tamil Nadu section open as targeted.
- Medium-term, on paper: Nelamangala, Magadi and Ramanagara, on the Obalapura–Kunigal package, which has been re-tendered but not awarded. Credible, but not yet a road. See Nelamangala, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks
- Uncertain: Kanakapura and Anekal on the southern arc, where the Bannerghatta section depends on forest and environmental clearances. Value property here on today's access. See Kanakapura Road, Bangalore
How do you check an “on STRR” plot or villa claim?
The STRR is access-controlled, which means properties along it do not get direct access to the main carriageway. What matters is distance to the nearest interchange and the quality of the local road to it.
- Ask for the nearest interchange by name and drive the route yourself. A plot 500 metres from the highway but 8 km from an exit is not “on STRR”.
- Ask which package the stretch falls in, and check its status against this page. Pay no premium for a package that is only tendered.
- Check that the layout is approved by the competent planning authority and, for plotted developments that require it, registered on Karnataka RERA.
- Check the land records for the survey number, including any acquisition notification for the highway itself.
- Treat appreciation percentages in brochures as marketing unless they cite a named, dated source.
Our view
The STRR's eastern half is real infrastructure that is nearly continuous from Dobbaspet to Hosur; the western and southern arc is a credible plan with uncertain timing. Buy in the satellite towns on current access, not the full ring. Related reading: the second-airport question, which also involves the Nelamangala and Kanakapura belts, at Second Airport Bangalore Location: Harohalli vs Nelamangala 2026