The Namma Metro Pink Line's first stretch, the 7.5 km elevated section from Kalena Agrahara to Tavarekere, is expected to be inaugurated in mid-November 2026: reports of 2 November give both 13 November, during the Prime Minister's visit, and 15 November, and BMRCL has not announced the date. It received its safety clearance from the Commissioner of Metro Railway Safety (CMRS) on 28 October (Oneindia and Asianet Newsable, 2 November 2026). The 12 underground stations, Dairy Circle to Nagawara, are targeted for May 2027 (Oneindia, 19 October 2026).
Updated 3 November 2026. What changed since 18 October: the CMRS clearance came through on 28 October, the Chief Minister proposed 15 November, and MP Tejasvi Surya has since posted 13 November; BMRCL had not announced the inauguration date or when public services start as of 3 November. For the underground section, BMRCL now gives May 2027 as the target. Homes on our listings near the southern stations include Godrej Vanantara, Prestige Southern Star and Casagrand Amor.
Status as of 3 November 2026
- Open now: no Pink Line station is open to passengers yet.
- Safety inspection: the CMRS (Southern Circle) inspected the six elevated stations from 6 to 8 October 2026 (The Bengaluru Live, 8 October). His letter of 9 October listed 36 observations covering civil works, electrical and traction systems, signalling, rolling stock and operations, including fire safety, lifts and earthing (Deccan Herald, 15 October).
- Compliance and clearance: BMRCL submitted compliance documents on all 36 observations on 15 October (Deccan Herald, 16 October), and the section received CMRS safety clearance on 28 October (Oneindia, 2 November). Minister Krishna Byre Gowda said the state is ready to open it as soon as the Union Government finalises the date (The Hans India, 2 November).
- Opening date: inauguration expected in mid-November 2026. MP Tejasvi Surya posted 13 November and Chief Minister D K Shivakumar had proposed 15 November (Asianet Newsable, 2 November); BMRCL has not announced the date. BMRCL and the state are expected to announce the operational schedule.
- On opening day: the network grows to 103.6 km, the second-longest in India, and Jayadeva Hospital becomes the city's third interchange. Six trains will run every 6 minutes at peak and every 10 minutes off-peak (Deccan Herald, 12 October).
- Feeder buses: BMTC plans five dedicated feeder routes to Hulimavu, Tavarekere, Jayadeva Hospital and JP Nagar 4th Phase, with 30 buses making 415 trips a day at 10-minute intervals (Deccan Herald, 12 October).
- Not yet open: the 12 underground stations, Dairy Circle to Nagawara (13.76 km). Systems work is nearly complete and trial runs are expected from November 2026 (Deccan Herald, 5 October 2026); BMRCL is aiming to open the section by May 2027, subject to testing and safety clearances (Oneindia, 19 October 2026).
- Fares and timings: not yet published by BMRCL.
All 18 Pink Line stations
South to north, per Wikipedia's Pink Line station table (6 elevated, 12 underground, 21.25 km), with status as of 3 November 2026. Station · locality served · elevated or underground · status:
- 1. Kalena Agrahara · Gottigere, southern Bannerghatta Road · elevated · CMRS-cleared, inauguration expected mid-November.
- 2. Hulimavu · Hulimavu and Arekere · elevated · CMRS-cleared, inauguration expected mid-November.
- 3. Bilekahalli IIM-B · Bilekahalli, IIM Bangalore · elevated · CMRS-cleared, inauguration expected mid-November.
- 4. JP Nagar 4th Phase · JP Nagar · elevated · CMRS-cleared, inauguration expected mid-November; planned interchange with the Phase 3 Orange Line.
- 5. Jayadeva Hospital · Jayadeva junction, near BTM Layout · elevated · CMRS-cleared, inauguration expected mid-November; interchange with the Yellow Line.
- 6. Tavarekere · Swagath Road Cross, near BTM Layout · elevated · CMRS-cleared, inauguration expected mid-November; end of the first section.
- 7. Dairy Circle · Hosur Road at Dairy Circle · underground · under construction, target May 2027; proposed Red Line interchange.
- 8. Lakkasandra · Lakkasandra · underground · under construction, target May 2027.
- 9. Langford Town · Langford Town · underground · under construction, target May 2027.
- 10. National Military School · Hosur Road, near the National Military School · underground · under construction, target May 2027.
- 11. Mahatma Gandhi Road · MG Road, central business district · underground · under construction, target May 2027; interchange with the Purple Line.
- 12. Shivajinagar · Shivajinagar · underground · under construction, target May 2027.
- 13. Cantonment Railway Station · Cantonment · underground · under construction, target May 2027; interchange with Indian Railways.
- 14. Pottery Town · Pottery Town · underground · under construction, target May 2027.
- 15. Tannery Road · Tannery Road · underground · under construction, target May 2027.
- 16. Venkateshpura · Venkateshpura · underground · under construction, target May 2027.
- 17. Kadugundanahalli · Kadugondanahalli · underground · under construction, target May 2027.
- 18. Nagawara · Nagawara, on the Outer Ring Road · underground · under construction, target May 2027; interchange with the Blue Line.
The Pink Line at a glance
- First section: Kalena Agrahara (Gottigere) to Tavarekere (Swagath Road Cross), 7.5 km, elevated, six stations (NativePlanet, 2 October 2026).
- Opening: CMRS safety clearance on 28 October 2026; inauguration expected in mid-November 2026, with reports giving 13 or 15 November (Oneindia and Asianet Newsable, 2 November 2026). The start of public services had not been announced by BMRCL as of 3 November.
- Frequency: every 6 minutes at peak and 10 minutes off-peak, with six trains, per Deccan Herald (1 October 2026) and Urban Acres (7 October 2026). Business Today had earlier reported three to four trainsets at launch.
- Fares: BMRCL has not published Pink Line fares. The network uses distance-based fares, and the Pink Line is expected to follow them; check BMRCL's fare chart at opening.
- Interchanges: Yellow Line at Jayadeva Hospital (to RV Road, Silk Board and Electronic City); the future Orange Line at JP Nagar 4th Phase (Wikipedia).
- Full line: 21.25 km from Kalena Agrahara to Nagawara. The underground section, Dairy Circle to Nagawara, is targeted for May 2027 (Oneindia, 19 October 2026).
Where the Pink Line stands today
- Elevated section, Kalena Agrahara to Tavarekere: 7.5 km with six stations, per NativePlanet's report of 2 October 2026. The CMRS inspection ran from 6 to 8 October 2026: a motor trolley inspection of the mainline, the Kothanur depot and train tests, then the operations control centre at Baiyappanahalli (Deccan Herald, 1 October 2026). NativePlanet reported on 8 October that the inspection had wrapped.
- Approvals already in hand before the inspection, per Deccan Herald: the RDSO speed certificate (August), the Railway Board's provisional rolling stock sanction and the independent safety assessor's certificate for signalling.
- Safety clearance: the CMRS cleared the elevated section on 28 October 2026 (Oneindia, 2 November 2026); NativePlanet (24 August 2026) had noted an interim speed certificate issued on 12 August.
- Underground section, Dairy Circle to Nagawara: 13.76 km with 12 underground stations. BMRCL now aims to open it by May 2027 (Oneindia, 19 October 2026); Deccan Herald (5 October 2026) adds that trial runs are planned from November and that it will be Bengaluru's first line with platform screen doors. Together the two sections make the 21.25 km full line.
- Rolling stock: Business Today reported eight trainsets received, with three to four likely to be deployed initially.
- Network effect: Deccan Herald (1 October 2026) says the elevated stretch will take the network to 103.6 km, making it the second-longest metro network in India.
What we do not know yet
BMRCL had not announced the date public services start as of 3 November 2026. The CMRS clearance is in place and the inauguration is expected in mid-November (reports give 13 or 15 November); fares and first and last train times are usually published at opening. Treat any specific day you read on a social post as unconfirmed until BMRCL publishes it.
The underground May 2027 date is a target, subject to testing and safety clearances, so plan around a range rather than a single date.
The six elevated stations and the neighbourhoods around them
The stations on the first section, per NativePlanet (2 October 2026), are Kalena Agrahara (Gottigere), Hulimavu, IIM-Bangalore, JP Nagar 4th Phase, Jayadeva Hospital and Swagath Road Cross (Tavarekere). Reading them as a south Bengaluru spine:
- Kalena Agrahara and Hulimavu: the Bannerghatta Road southern stretch, where metro access is new and the benefit is largest for daily commuters currently reliant on a heavily congested road. Guides: Bannerghatta Road, Bangalore and Hulimavu and Arekere, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks
- IIM-Bangalore and JP Nagar 4th Phase: an established residential belt. The JP Nagar 4th Phase station is also marked on Wikipedia's station table as a planned interchange with the future Phase 3 Orange Line, which is still years from operations (see our Phase 3 article). Guides: Jp Nagar, Bangalore and Living In Jp Nagar
- Jayadeva Hospital: an interchange with the Yellow Line per Wikipedia's Pink Line table, which links the Pink Line to the RV Road to Bommasandra corridor and so to Electronic City. Guide: Electronic City area guide
- Tavarekere (Swagath Road Cross): the current northern end of this first section, near BTM Layout, which means riders heading towards MG Road still need the underground stretch to complete the journey. Rates: Btm Layout
Price per sq ft near the southern stations
Indicative asking rates from named portals and reports, not transaction prices; portals disagree, so compare specific buildings. Locality · nearest Pink Line station · indicative rate:
- Bannerghatta Road (corridor) · Kalena Agrahara to Jayadeva Hospital · about ₹12,450 per sq ft, down about 3.2% on the quarter after a March 2026 peak near ₹12,850 (Square Yards, September 2026).
- Kalena Agrahara · Kalena Agrahara · about ₹11,400 per sq ft (Square Yards, September 2026).
- Gottigere · Kalena Agrahara · about ₹10,550 per sq ft (Square Yards, September 2026).
- Hulimavu · Hulimavu · about ₹11,400 per sq ft (Square Yards, September 2026); Homebazaar's May 2026 table shows about ₹7,350, which is why we treat any one figure with care.
- Arekere · Hulimavu · about ₹9,250 per sq ft (Square Yards, September 2026).
- JP Nagar · JP Nagar 4th Phase · about ₹11,350 per sq ft (Square Yards, September 2026).
- BTM Layout · Jayadeva Hospital and Tavarekere · about ₹12,800 per sq ft (Homebazaar, May 2026).
- New launch example: ANAROCK's Q2 2026 report lists Godrej Vanantara on Bannerghatta Road (2,008 units) at about ₹12,000 per sq ft among the quarter's key launches.
- Locality pages: Bannerghatta Road, Jp Nagar, Btm Layout and Hulimavu and Arekere, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks
The underground section and why it matters more
A line that stops at Tavarekere is useful but incomplete. The underground section runs from Dairy Circle through Lakkasandra, Langford Town, National Military School, Mahatma Gandhi Road, Shivajinagar, Cantonment Railway Station, Pottery Town, Tannery Road, Venkateshpura and Kadugundanahalli to Nagawara, per Wikipedia's station table. It brings the line to Mahatma Gandhi Road (an interchange with the Purple Line) and, at the other end, to Nagawara where the Blue Line is expected to connect.
For a buyer the practical reading is simple: the first section improves access to the south; the full line is what makes south Bengaluru to the central business district and north Bengaluru a one-line journey. The second part has not yet been delivered.
What this does to south Bengaluru property, honestly
The most defensible effects are on rentals and end-user demand along the corridor, because commute time is the main variable the line changes. Published research from Mumbai (Suri and Cropper, University of Maryland dissertation) found price increases of 13 to 17 percent within 1 km of the first Mumbai metro line against control areas 1 to 3 km away, but that was a single, different city with its own conditions, and it is not a forecast for Bengaluru.
A Bengaluru-specific hedonic study (Ballal and Tripathi, 2025) found that proximity to metro stations raises housing values, and that areas where the metro had operated longer and development was denser saw stronger gains. The inference for a line that is only about to open is cautious: gains are not automatic and take time.
Be wary of broker claims of instant double-digit appreciation. By the time a station opens, pockets near it have often already repriced, a point PropNewz made about the Yellow Line corridor in June 2026.
A buyer's checklist for Pink Line corridors
- Measure the real walking route to the station entrance, not the straight-line distance. Footpaths and crossings on Bannerghatta Road matter.
- Verify the project's K-RERA registration and its possession date; a metro station does not fix a late or unapproved project.
- Compare the all-in price per square foot of carpet area with similar projects 2 to 3 km further from the station to see how much premium you are being asked to pay.
- Ask how the home will be used. For self-use the commute saving is the benefit; for rental the tenant pool near an IT or institutional employer is the benefit.
- Do not underwrite the purchase on the May 2027 underground date. Underwrite it on the building, the location and the price.
Our view
The Pink Line is real, days from its first opening, and a genuine improvement for Bannerghatta Road and JP Nagar. The calm approach is to treat the metro as one of several reasons to like a micro-market, not the only one, and to let the delivered service rather than the announcement decide how much you pay.