Metro & property · Bengaluru

Namma Metro: live status, stations & timings

Our reporting on Namma Metro, line by line: what is open, what is under construction, and what each corridor means for the homes around its stations.

Status checked

The line

  • Testing
  • Being built

Station 1 of 18

Kalena Agrahara

Built · awaiting safety authorisation

Line status

Checked

Pink Line, Bengaluru

  • Kalena Agrahara – Tavarekere (elevated)

    7.5 km · 6 stations

    Inspected by the Commissioner of Metro Rail Safety on 6–8 October. Passenger service starts once the authorisation is issued; no opening date has been announced.

    Safety inspection

    Target Late Oct or early Nov 2026Reported, Vartha Bharati, 18 Oct 2026

  • Dairy Circle – Nagawara (underground)

    13.8 km · 12 stations

    Track laid; trial runs expected in November–December.

    Under construction

    Target March 2027BMRCL, via Deccan Herald, 5 Oct 2026; May 2027 in a later report

Latest

  1. The Chief Minister has invited the Prime Minister to open the elevated stretch; 1 November is under consideration. Vartha Bharati

  2. BMRCL is answering the 36 observations from the safety inspection before authorisation. Deccan Herald

  3. BMTC set out five feeder bus routes for the Pink Line stations: 30 buses, every 10 minutes. Deccan Herald

The line

  • Being built

Station 6 of 28

Embassy TechVillage Devarabeesanahalli

Under construction

Line status

Checked

Blue Line, Bengaluru

  • Central Silk Board – KR Puram (Phase 2A)

    19.75 km · Outer Ring Road

    Trial runs, KR Puram to Marathahalli first, now expected in November.

    Under construction

    Target 2027March 2027 (minister, Deccan Herald, 18 Aug 2026); May 2027 in a later report

  • Hebbal – Airport (Phase 2B)

    27.4 km

    Under construction

    Target Not before Sept 2027Deccan Herald, 19 Aug 2026

  • KR Puram – Hebbal (Phase 2B)

    11 km

    Under construction

    Target December 2027Deccan Herald, 19 Aug 2026

Latest

  1. BMRCL is preparing trial runs from Byappanahalli depot to KR Puram and Marathahalli; all Phase 2A stations except Silk Board due to finish by November. Urban Acres

The line

  • Open

Station 3 of 16

Jayadeva Hospital

Open

Change here for the Pink Line

Line status

Checked

Yellow Line, Bengaluru

  • RV Road – Bommasandra

    19.15 km · 16 stations

    Every 7 minutes at weekday peak, 10 minutes off-peak and at weekends. First train 6 am (7 am on Sunday); last trains 11:55 pm from RV Road and 10:42 pm from Bommasandra. Confirm in the Namma Metro app.

    Open

    Since 11 Aug 2025

Latest

  1. Services across the network ran until 1:30 am for the India–West Indies T20 match, a one-off extension. Deccan Herald

Station by station

Every station, and the homes within 2 km

Our reporting, line by line

Pink Line

Kalena Agrahara to Nagawara, through Tavarekere and the Cantonment.

Yellow Line

RV Road to Bommasandra, along Hosur Road and Electronic City.

Blue Line

Silk Board to KR Puram along the Outer Ring Road, and on to the airport.

Red Line and Phase 3

Hebbal to Sarjapur, and the Orange and Grey lines of Phase 3.

Suburban rail

K-RIDE's Mallige Line and the areas it serves.

Metro and prices

What the evidence says about homes near stations.