Chennai Metro Phase 2 is being completed in sections, with the last ones targeted for 2028; only Poonamallee Bypass to Vadapalani on Corridor 4 is open, since 11 October 2026. Next in line are the Red Line's Koyambedu to Chennai Trade Centre stretch (trials targeted from November 2026) and Vadapalani to Panagal Park (targeted for March 2027). The OMR section of Corridor 3 is planned for 2027, and the underground city sections point to 2028.
Updated 5 November 2026. This page is now our station-by-station tracker, built from CMRL's own press releases (P.R. 62 to 70 of 2026, 29 September to 2 November) plus dated press reports where CMRL has published nothing. New: the CMRL list of the 11 open stations; a 29 October report (The Hindu, via Swarajya) that the six skipped Corridor 4 stations are now likely by March 2027; CMRL's 31 October statement that Porur–Vadapalani services continue as usual (DT Next); a CMRL Metro Connect shuttle from Porur Bypass station from 2 November; and the latest Corridor 3 and 5 construction milestones. As of 5 November we found no report that Koyambedu trials have started.
Earlier update, 3 November 2026. We rechecked the reports and Wikipedia on 3 November. What changed: trains on the open stretch run 6 am to 9 pm from 23 October (DT Next, 21 October 2026), and Wikipedia's tables now show March 2027 for the six unopened Corridor 4 stations and for Koyambedu to Alandur. We found no report yet that Koyambedu trials have started, and no new CMRL date for any section. Every date below is labelled as a target unless it has already happened, with its source and date.
Homes on our listings along the Phase 2 lines include Appaswamy Skylon, Navin's Mayura Gardens, Urbanrise Whispers of Sky and Radiance Solitaire.
Chennai Metro Phase 2 stations open now (CMRL, November 2026)
CMRL's release of 10 October 2026 (P.R. 66/2026) lists the 11 elevated stations on Corridor 4 where regular passenger service began on 11 October, over about 15 km from Poonamallee Bypass to Vadapalani. In order from the Poonamallee end:
- 1. Poonamallee Bypass · open since 11 Oct 2026
- 2. Poonamallee Bus Stand · open since 11 Oct 2026
- 3. Poonamallee Government Hospital · open since 11 Oct 2026
- 4. Karayanchavadi · open since 11 Oct 2026
- 5. Kumananchavadi · open since 11 Oct 2026
- 6. Kattupakkam · open since 11 Oct 2026
- 7. Iyappanthangal · open since 11 Oct 2026
- 8. Thelliyaragaram · open since 11 Oct 2026
- 9. Porur Bypass · open since 11 Oct 2026; CMRL Metro Connect shuttle to One Paramount, Porur, from 2 Nov 2026 (P.R. 70/2026)
- 10. Porur Junction · open since 11 Oct 2026
- 11. Vadapalani (Corridor 4) · open since 11 Oct 2026
- Timings: 6 am to 9 pm from 23 October 2026, last train 9 pm from both ends; every 10 minutes at peak (8–11 am and 5–8 pm, Monday to Saturday) and every 15 minutes otherwise and all day on Sundays and holidays (P.R. 68/2026, 21 Oct 2026). Before 23 October service started at 7 am (P.R. 66/2026).
Skipped stations between Porur Junction and Vadapalani: status and names
Trains pass through six stations between Porur Junction and Vadapalani that are not yet open. CMRL has not given an opening date in any release we found. The Hindu reported, as summarised by Swarajya on 29 October 2026, that CMRL is likely to seek time until March 2027, with an official saying about 95% of platform work was done; Wikipedia's Yellow Line table (read 5 November 2026) also shows March 2027. Earlier, a December 2026 target was reported (The New Indian Express via Metro Rail News, 11 October 2026).
Sources do not agree on the station names, so check against CMRL's signage and official list before relying on one:
- Named in every source we read: Alapakkam, Karambakkam, Valasaravakkam and Alwarthirunagar (Alwar Thirunagar).
- The Hindu, via Swarajya (29 Oct 2026): the other two are Saligramam Warehouse and Saligramam.
- Wikipedia (read 5 Nov 2026): the other two are Virugambakkam South and Saligramam.
- Our earlier updates, following October press reports, used Saligramam and Avichi School.
- Operating approval: the 29 October report said the safety commissioner's provisional authorisation for Porur–Vadapalani was valid until 31 October 2026. On 31 October CMRL dismissed reports that the authorisation had expired and said services would continue as usual with no change to the timetable (DT Next, 31 Oct 2026).
- Station-area guide: Is Valasaravakkam Metro Open? Opening Date (Nov 2026)
Latest CMRL construction milestones on Corridors 3 and 5
- 29 Sep 2026, Corridor 3: downline TBM 'Kaveri' broke through at Kilpauk Medical College station after a 685 m drive from Chetpet, the 9th breakthrough under the TU02 contract (P.R. 62/2026).
- 30 Sep 2026, Corridor 5: TBM 'Marutham' broke through at Villivakkam Bus Terminus station (north shaft) after 601 m from Villivakkam Railway station, under five railway tracks. Corridor 5's underground section has five stations (P.R. 63/2026).
- 1 Oct 2026, Corridor 3: downline TBM 'Adyar' broke through at RK Salai station after a 915 m drive from Royapettah, the 10th breakthrough under TU02, on the 12-km underground section between Kellys and Taramani (P.R. 65/2026).
- 13 Oct 2026, Corridor 5: all 3,126 precast elements cast for the Ullagaram–Sholinganallur elevated package (ECV-03), including 892 U-girders; work moves to erecting the remaining U-girders and building station entry and exit structures (P.R. 67/2026).
- None of these releases gives an opening date for the section concerned.
What was approved, and when was Phase 2 meant to be finished?
The Union Cabinet approved Phase 2 on 3 October 2024: 118.9 km across three corridors with 128 stations, at a completion cost of ₹63,246 crore, planned to be completed by 2027 (ETV Bharat's report of the Cabinet decision).
- Corridor 3, Madhavaram to SIPCOT (Purple Line): 45.8 km, 50 stations at approval.
- Corridor 4, Lighthouse to Poonamallee Bypass (Yellow Line): 26.1 km, 30 stations at approval.
- Corridor 5, Madhavaram to Sholinganallur (Red Line): 47 km, 48 stations at approval.
- Network after Phase 2: about 173 km in all, per the same report.
- Later figures differ. Propspedia (September 2026) cites a June 2026 CMRL update of 116.1 km and 118 stations, with completion targeted by the end of 2028. We have not seen that update ourselves, so treat the revised totals as reported.
Corridor 4 (Yellow Line): what is open, and what comes next?
- Poonamallee Bypass to Vadapalani, 14.6 km: open since 11 October 2026, with 11 stations in service (DT Next). This stretch was first targeted for December 2025, then February 2026; the Commissioner of Railway Safety gave approval in May 2026 (DT Next).
- Six stations on that stretch (Alapakkam, Karambakkam, Valasaravakkam and Alwarthirunagar, plus two whose names differ by source; see the section above): built into the line, opening later, no CMRL date. The latest report is March 2027 (The Hindu via Swarajya, 29 October 2026), replacing the December 2026 target reported on 11 October; Wikipedia also shows March 2027. Details: Is Valasaravakkam Metro Open? Opening Date (Nov 2026)
- Vadapalani to Panagal Park, 3.5 km underground: target March 2027. Swarajya reported on 3 February 2026 that tunnelling was complete, track-laying was about to begin, and Panagal Park station had reached concourse and platform level.
- Panagal Park to Lighthouse: Wikipedia's Yellow Line page shows June 2028 for the Vadapalani to Lighthouse section as a whole, with stations including Kodambakkam and Nandanam.
- What the open stretch means for buyers: Porur, Poonamallee Metro Opening Date & Stations (Nov 2026)
Corridor 5 (Red Line): when does Koyambedu to Alandur open?
This is the next section most likely to carry passengers. Swarajya reported in January 2026 that CMRL was working to bring the 12-km, 13-station Koyambedu to Butt Road stretch forward from June 2027 to June 2026; the current target is set out below.
The latest position is from Construction World on 8 September 2026. T Archunan, CMRL's director of projects, said nearly 90% of the track work on the Koyambedu to Chennai Trade Centre section was done, with about 1.5 km left, including roughly 300 metres on the double-decker stretch. Trials were targeted for November, followed by about four months of testing before commercial service, with driverless trains planned.
- Koyambedu to Chennai Trade Centre: trials targeted by end-November 2026 (Metro Rail News, 11 October 2026); with four months of testing, passenger service would fall in 2027 at the earliest. As of 5 November 2026 we found no report, and no CMRL release, saying trials had started.
- Chennai Trade Centre to Alandur, about 3.6 km along Butt Road: officials told Construction World it was unlikely before 2027, possibly in the first quarter. Wikipedia's Red Line table (rechecked 3 November 2026) shows March 2027 for Koyambedu to Alandur.
- The southern section to Sholinganallur (via Madipakkam, Kovilambakkam and Medavakkam) and the northern section from Madhavaram: we found no recent CMRL date. Wikipedia shows December 2027 for the Sholinganallur end and December 2028 for Madhavaram; treat any specific month you see quoted as unconfirmed.
- Stations and localities on the Red Line: Madhavaram to Sholinganallur Metro: Route, Dates (Nov 2026)
Corridor 3 (Purple Line): what is the OMR metro completion date?
The elevated OMR section has the most visible progress; the underground city section has the longest road ahead.
- OMR elevated section, Nehru Nagar (Perungudi) to SIPCOT Siruseri, about 20 km: CMRL said in 2023 that it planned to run this section by 2027 (India Infra Hub, 30 May 2023). Propspedia (September 2026) describes a December 2026 target after an earlier June 2026 plan. We have not seen CMRL confirm December 2026.
- Progress on that section: Swarajya reported on 18 July 2026 that all 3,066 piles and 582 U-girders were complete on the Nehru Nagar to Sholinganallur stretch, built by Larsen & Toubro under package C3/EV-01. Tracks, systems, stations and testing still follow.
- Underground section, Madhavaram to Taramani: India Infra Hub reported in April 2023 that this stretch was expected in 2028. Tunnelling continues; DT Next reported the eighth tunnel breakthrough under the TU-02 contract, at Mandaveli, on 7 February 2026.
- OMR stations and homes near them: Purple Line Metro Chennai: Stations, Completion (Nov 2026)
Chennai Metro Phase 2 status at a glance
Section · status on 5 November 2026 · latest target and source:
- Poonamallee Bypass–Vadapalani · open (11 stations), 6 am to 9 pm from 23 October · opened 11 October 2026 (CMRL P.R. 66/2026 and 68/2026).
- Six Corridor 4 stations between Porur Junction and Vadapalani · built, not open · March 2027 reported (The Hindu via Swarajya, 29 Oct 2026; Wikipedia); no CMRL date.
- Vadapalani–Panagal Park · tunnels done · March 2027 target (Swarajya, February 2026).
- Panagal Park–Lighthouse · under construction · June 2028 (Wikipedia).
- Koyambedu–Chennai Trade Centre · track about 90% done · trials November 2026, service after about four months of tests (Construction World).
- Chennai Trade Centre–Alandur · under construction · possibly Q1 2027 (Construction World); March 2027 on Wikipedia.
- Nehru Nagar–SIPCOT (OMR) · piling and girders done to Sholinganallur · 2027 plan (CMRL via India Infra Hub, 2023); December 2026 reported by Propspedia.
- Madhavaram–Taramani (underground) · tunnelling under way · 2028 (India Infra Hub, 2023; Propspedia, 2026).
Why do Chennai metro sections open in stages?
The reports point to the ordinary sequence of a large urban metro rather than one factor. The Poonamallee stretch shows it clearly: civil work, then safety clearance, then station finishing, then a formal opening. It received its final safety approval in May 2026 and opened five months later.
- Dense, narrow roads. Swarajya noted in January 2026 that work on parts of Butt Road is planned around narrow carriageways, with night-only work near the Kathipara flyover.
- Complex stations. The double-decker stations on Arcot Road, shared by two lines, are finished after the viaduct.
- Tendering and funding steps. India Infra Hub reported in 2023 that tendering and lender approvals were part of the timeline for the underground Corridor 3 work.
- The last step takes time. Trials, safety inspection and an inauguration date can add months after the track is ready.
How should a homebuyer use these dates?
- Treat a trial run as the start of the countdown, not the end. On Corridor 5, CMRL itself expects about four months of testing after trials begin.
- Allow a margin between a target and an opening. The Poonamallee stretch was first targeted for December 2025 and opened on 11 October 2026.
- Pay for open stations, not for future ones. Where a station is a 2027 or 2028 target, the price should reflect that.
- Check station names against CMRL signage and the approved station list; names were revised in places.
- Prices along the lines have not moved in step with dates; see what the 2026 data shows: Chennai Real Estate Market 2026: Up 22% or Down 17%?
- Shortlisting in the west or south during the monsoon? Use Chennai Flood 2026: Monsoon Site-Visit Checklist for a Flat
- Station-by-station map of homes: Metro Stations Chennai