Just three RERA-registered projects in our mapped catalogue sit within 1 km of the 12 underground Pink Line stations from Dairy Circle to Nagawara, and all three are small, ready luxury buildings in the old city: Prestige Deja Vu near Cantonment, Sobha 25 Richmond near National Military School and Prestige Kenilworth near Shivajinagar. The 13.76 km underground section has trial runs planned for November–December 2026 and a latest deadline of March 2027 (Deccan Herald, 3 November 2026).
Updated 8 November 2026. We measured every mapped Bengaluru project against each underground station and checked the latest dated reports on the opening. For the station-by-station construction story, see Pink Line Underground: 12 Stations, Trials, March 2027 Target.
When will the Pink Line underground open?
So the dates on record run from March to mid-2027. The elevated section from Kalena Agrahara to Tavarekere opens first, on 13 November 2026, with public service from 14 November.
- Deccan Herald, 3 November 2026: systems installation in the final leg, trial runs planned November–December, latest deadline March 2027.
- The Hindu, 4 November 2026: BMRCL is targeting the first half of 2027 for the entire Pink Line, subject to testing and statutory clearances; hard rock and underground obstructions slowed the work.
- Our metro status file (20 October 2026) records March 2027 from BMRCL via Deccan Herald (5 October 2026) and May 2027 in a later report.
The 12 underground stations and registered homes nearby
Straight-line distance from station to project address. Projects within 1 km first; projects between 1 and 1.5 km in brackets.
- Dairy Circle — none within 1.5 km.
- Lakkasandra — none within 1.5 km.
- Langford Town — none within 1 km (Sobha 25 Richmond 1.1 km; Century Renata, PRM/KA/RERA/1251/446/PR/170918/000782, 36 homes, ready, 1.35 km).
- National Military School — Sobha 25 Richmond, PRM/KA/RERA/1251/446/PR/170916/000257, 7 homes, ready, 0.98 km — Sobha 25 Richmond (Century Renata 1.25 km).
- MG Road (interchange with the Purple Line) — none within 1.5 km in our mapped set.
- Shivajinagar — Prestige Kenilworth, PRM/KA/RERA/1251/309/PR/170915/000208, 42 homes, 0.90 km (Prestige Deja Vu 1.4 km).
- Cantonment Railway Station — Prestige Deja Vu, PRM/KA/RERA/1251/309/PR/170913/000129, 40 homes, ready, 0.52 km — Prestige Deja Vu (Prestige Kenilworth 1.2 km).
- Pottery Town — Prestige Deja Vu, 0.55 km.
- Tannery Road — none within 1.5 km.
- Venkateshpura — none within 1.5 km.
- Kadugundanahalli — none within 1.5 km with an exact pin.
- Nagawara (future interchange with the Blue Line) — none within 1 km (Casagrand Orlena, PRM/KA/RERA/1251/446/PR/210928/004324, 296 homes, ready, 1.14 km — Casagrand Orlena).
Why buyers overlook these stations
The underground runs beneath the city's densest, oldest neighbourhoods, from Richmond Town and Langford Town through Shivajinagar, Frazer Town and Tannery Road to Nagawara. New registered supply there is scarce and comes as small, high-value buildings, which is why the count is low and the homes are few: the three projects within 1 km hold 89 homes between them.
Interchanges will shape who benefits first. MG Road links to the Purple Line, which runs to Whitefield and Challaghatta without a change; Nagawara is planned as an interchange with the Blue Line towards Hebbal and the airport, whose Hebbal–Airport stretch is not expected before September 2027 (Deccan Herald, 19 August 2026, via our metro status file). Cantonment station takes its name from the railway station beside it, giving a rail-to-metro change in the middle of the corridor.
The station that matters most for new supply is Nagawara, at the northern end, where the Pink Line will meet the Blue Line to the airport. Projects on Hennur Road and Thanisandra sit 1–3 km from it; see Nagawara, Bangalore and Hennur Road, Bangalore. Two catalogue projects near Nagawara Junction and Hennur Road Extension, Casagrand Regal and Assetz Mizu & Ki, are pinned only to their locality centre, so we have not counted them.
Data note: how we counted
- Stations: the 12 underground Pink Line stations with coordinates from src/data/blr-metro.ts (October 2026).
- Projects: 199 Bengaluru projects in the Property Point catalogue (read 8 November 2026) with a pin at the project's own address (project-pins.json, checked 28 October 2026). Projects pinned to a locality centre are not counted.
- Distance: straight-line. Homes: unit counts from our October 2026 project check. Status: ready-to-move where our catalogue says so.
- Limits: a curated catalogue of about 400 projects, not the whole K-RERA register.