Gurgaon has one new metro line under construction: GMRL's Millennium City Centre to Cyber City loop. Piling began on 27 November 2025, and Phase 1 is targeted for 2028. Two more lines are in planning: the 28-station Sector 56 to Panchgaon line, which is close to final approval, and a 17-station Bhondsi to Railway Station line that RITES proposed in June 2026. The airport-line link and two Namo Bharat corridors are at DPR stage or awaiting approval.
Updated 3 November 2026. We read the latest HMRTC board report (8 October 2026), NCRTC's 18 October statement and the June 2026 reports on each new proposal. Every line below is shown with its stage and the date of the source. Stations on lines not yet sanctioned can still change.
Which metro lines are coming to Gurgaon?
Ranked from most advanced to least, as of 3 November 2026:
- Millennium City Centre–Cyber City loop, Phase 1 (MCC to Sector 9, with a spur to Dwarka Expressway): under construction. Piling started at Sector 44 on 27 November 2025, with a 2028 target for the first phase (Swarajya, 28 November 2025).
- Same loop, Phase 2 (Sector 9 to Cyber City through Old Gurgaon): civil tender issued in October 2026. See Gurugram Metro Phase 2: Sector 9 to Cyber City Route and Stations.
- Delhi–Gurugram–Bawal Namo Bharat (RRTS): approved by the Union housing ministry in January 2026 (Metro Rail Today, 27 January 2026). NCRTC said on 18 October 2026 that the corridor is 'likely to receive approval soon'.
- Sector 56–Panchgaon metro: a 35.25 km elevated line with 28 stations, 'moving through the final stages of approval' (ThePrint/PTI, 8 October 2026).
- Gurugram–Faridabad–Noida–Greater Noida Namo Bharat: at DPR stage (NCRTC, 18 October 2026). Gurugram and Faridabad stations are finalised at state level (ThePrint/PTI, 8 October 2026).
- Airport Express extension into Gurugram: DMRC draft DPRs, under review by the Union housing ministry (Construction World, 29 June 2026; Swarajya, 15 July 2026).
- Bhondsi–Gurugram Railway Station metro: tentative 20 km, 17-station route proposed by RITES; DPR stage (Swarajya, 17 June 2026).
- Sector 5–Golf Course Extension Road metro via Sheetla Mata Road: about 13 km; the HMRTC board approved preparing a DPR in August 2024 (Swarajya, 19 August 2024).
- MG Road–Sector 95 link via Global City and Vision City: feasibility study by RITES (Swarajya, 23 June 2026).
What runs in Gurgaon today?
Two lines run now. The Delhi Metro Yellow Line ends at Millennium City Centre. The Rapid Metro loops through Cyber City and down Golf Course Road to Sector 55-56, meeting the Yellow Line at Sikanderpur. Rapid Metro carried 88.81 lakh passengers from April to August 2026, up from 79.57 lakh a year earlier (ThePrint/PTI, 8 October 2026).
Everything else on this page is either under construction or a plan. For how the Rapid Metro, the new loop and the proposals fit together, see Gurugram Metro 2026: Millennium City Centre-Cyber City Line Status and Sectors It Serves.
What are the stations of the new Gurgaon metro, Phase 1?
Phase 1 is 15.22 km with 15 stations and a 1.85 km spur towards Dwarka Expressway (India TV, 7 July 2025). India TV names 13 of the stations to be built first:
- Sector 45, Cyber Park (Sector 46), Sector 47, Subhash Chowk, Sector 48
- Sector 33, Hero Honda Chowk, Udyog Vihar Phase 6, Sector 10, Sector 37
- Basai, Sector 9, Sector 101
A depot is planned in Sector 33. Swarajya's November 2025 report gives 14 stations for the elevated stretch and a Phase 1 civil cost of ₹1,277 crore. Station counts differ between reports because some include the spur or the Sector 9 junction. For Phase 2's 13 stations from Sector 7 to Cyber City, see our Phase 2 explainer.
What new metro lines were proposed for Gurgaon in 2026?
Three proposals came forward between March and July 2026. None of them is sanctioned.
- Bhondsi to Gurugram Railway Station (June 2026): RITES suggested a tentative 20 km route with 17 stations through Badshahpur, Sector 67, M3M Urbana Chowk, Sector 65, Golf Course Extension Road, South City II, Medanta and Sadar Bazar. It would end at the railway station via an interchange at Sector 5. Two more route options are still under study (Swarajya, 17 June 2026). Full station list: Bhondsi Metro Route 2026: 17 Stations to Railway Station.
- Airport Express into Gurugram (June–July 2026): DMRC put two draft DPRs before HMRTC's 65th board meeting. One runs from Yashobhoomi to Rajiv Chowk along NH-48, the other from Dwarka Sector 21 to Sector 21, Gurugram (Construction World, 29 June 2026). The routes were then merged into one 20 km underground plan with stops at Bijwasan, Kapashera, Sector 22, IFFCO Chowk and Rajiv Chowk, costed at nearly ₹13,500 crore (Swarajya, 15 July 2026). Details: Dwarka Expressway Metro 2026: Airport Line Routes.
- MG Road to Sector 95 (June 2026): RITES is running a feasibility study for a corridor via Sohna Bus Stand, Umang Bhardwaj Chowk, Gadoli, Global City, Vision City (Sector 88) and Sector 92, ending at Sector 95 near Wazirpur (Swarajya, 23 June 2026). No length or station count has been published.
Where does the Sector 56 to Panchgaon metro stand?
It is the most advanced of the new proposals. The final DPR is complete and was due to go to the Chief Minister (Construction World, 29 June 2026). On 8 October 2026 the HMRTC board heard that the 35.25 km, 28-station elevated corridor was moving through the final stages of approval and would link with the Namo Bharat network (ThePrint/PTI). We cover its route along Golf Course Extension Road, SPR and the Dwarka Expressway sectors in Sector 56 to Panchgaon Metro 2026: Route, 28 Stations, Status.
Which Namo Bharat (RRTS) lines will serve Gurgaon?
- Delhi–Gurugram–Bawal, with a proposed extension to Behror: on 22 September 2026 Haryana added the revised Sarai Kale Khan–Gurugram–Bawal corridor to its transit-oriented development (TOD) policy (UNI, 23 September 2026). The Gurugram stations listed are Cyber City, Iffco Chowk, Rajiv Chowk, Hero Honda Chowk, Kherki Daula, Manesar, Panchgaon and Bilaspur (Urban Acres, 29 September 2026). Status and stations: Delhi Gurgaon Alwar RRTS 2026: Route, Status, Stations.
- Gurugram–Faridabad–Noida–Greater Noida: a 64 km corridor with 7 Namo Bharat stations and 15 metro stations proposed (NCRTC). In Gurugram it is planned from IFFCO Chowk towards Gwal Pahari. Route and stations: Namo Bharat Gurgaon to Noida 2026: Route, Stations, Status.
- Land within 1.5 km of the Bawal-line stations now falls under TOD rules. What that means for buyers: TOD Zone Gurugram 2026: 1.5 km Namo Bharat Rules for Buyers.
Gurgaon metro map: which areas each line serves
- Golf Course Road and Sectors 52 to 58: Rapid Metro today; Gurugram–Noida Namo Bharat stops proposed at IFFCO Chowk, Sector 58/61 and Gwal Pahari.
- Golf Course Extension Road (Sectors 61 to 67): proposed Sector 56–Panchgaon line; the tentative Bhondsi line through Sectors 65 and 67.
- Sohna Road (Sectors 47 to 49, South City II): Phase 1 stations at Sectors 47 and 48 and Subhash Chowk; the tentative Bhondsi line through South City II and Sector 47.
- Dwarka Expressway: Phase 1's Sector 101 end and its 1.85 km spur; the proposed Panchgaon line's Dwarka Expressway sectors; the airport-line options at the Delhi end.
- NH-48, Manesar and beyond: Namo Bharat stations proposed at Hero Honda Chowk, Kherki Daula, Manesar, Panchgaon and Bilaspur.
- Old Gurgaon: Phase 2 of the loop; the Bhondsi line's northern end at Sadar Bazar and the railway station.
Registered projects near the upcoming lines
Each of these is registered with HARERA Gurugram. Distances to a future station depend on the final alignment, so measure from the sanctioned drawings once they are out, not from a proposal map. For more of the market, see New Launches, Gurgaon and Golf Course Extension Road, Gurgaon.
- M3M Altitude — Sector 65, Golf Course Extension Road — price on request (our listing, checked October 2026) — possession Jul 2031 — RERA GGM/821/553/2024/48. Sector 65 is on the tentative Bhondsi route. See M3M Altitude.
- Smartworld Sky Arc — Sector 69 — price on request (our listing, checked October 2026) — possession May 2032 — RERA GGM/878/610/2024/105. In the Golf Course Extension Road and SPR belt the Panchgaon line is planned to serve. See Smartworld Sky Arc.
- Elan The Statement — Sector 49, Sohna Road — price on request (our listing, checked October 2026) — possession Sep 2033 — RERA GGM/1022/754/2025/125. See Elan The Statement.
- Adani The Marq — Sector 102A, Dwarka Expressway — from ₹4.6 Cr (our listing, checked November 2026) — possession Dec 2031 — RERA GGM/1042/774/2026/14. See Adani The Marq.
- Signature Global Twin Tower DXP — Sector 84 — from ₹5.3 Cr (our listing, checked October 2026) — HARERA completion May 2030 — RERA GGM/866/598/2024/93. See Signature Global Twin Tower DXP.
How should a buyer read a metro proposal?
- Know the stage. The order runs: proposal, feasibility study, DPR, state approval, central approval and funding, tender, construction. Only the last two give you a dated plan.
- Use the official date. For a home, use the RERA completion date on HARERA Gurugram. For a metro, use the date in the sanction or tender.
- Station names on proposals are indicative. The Bhondsi route already has three options under study.
- Price the home on what exists today: roads, the Rapid Metro, the Yellow Line. Treat a future station as a possible benefit, not something already in the price.